32
Installation and maintenance instructions ecoTEC exclusive 0020193968_05
Note
All radiators should be cold before you start
calibration. This ensures that the heat
volume can be transferred to the heating
installation.
Note
If there is an excessive air temperature at
the radiators, calibration may not be pos-
sible.
3.
Start check programme
P.01
.
◁
The heat generator starts in heating mode.
◁
The heat generator first switches between status
S.01
and status
S.02
.
◁
The heat generator switches to status
S.93
after
approximately two minutes for calibration.
◁
Do not measure the CO/CO
₂
content or the gas
flow during calibration (status
S.93
).
Condition
: The flow temperature increases to above 80 °C in the next five to
six minutes.
▶
The heat generator does not switch to status
S.04
.
Note
Calibration is not complete and the CO/CO
₂
content and gas flow cannot be measured.
▶
Use
to end check programme
P.01
.
4.
Alternatives 1:
▶
If required, carry out calibration and measurement
again.
4.
Alternatives 2:
▶
Calibrate the heat generator and measure the
CO/CO
₂
content and the gas flow in domestic hot
water mode. (
→
Page 32)
Condition
: The flow temperature remains below 80 °C in the next five to six
minutes.
▶
If the heat generator switches from status
S.93
to status
S.04
after approximately five to six minutes, calibration at
maximum heat input is complete.
▶
In the next few minutes, measure the CO/CO
₂
content
and the gas flow at maximum load.
▶
Use
to end check programme
P.01
.
▶
Start check programme
P.02
.
◁
The heat generator starts in heating mode.
◁
The heat generator switches to status
S.93
after ap-
proximately two minutes for calibration.
◁
Do not measure the CO/CO
₂
content or the gas flow
during calibration (status
S.93
).
◁
If the heat generator permanently switches from
status
S.93
to status
S.04
after approximately two to
five minutes, calibration at minimum load is complete.
▶
In the next few minutes, measure the CO/CO
₂
content
and the gas flow at minimum load.
▶
Use
to end check programme
P.02
.
◁
Calibration and measurement in heating mode are
complete.
▶
Log the CO
₂
content (air ratio) and CO/CO
₂
ratio in the
Benchmark gas boiler commissioning checklist.
9.15.4.1 Calibrating the heat generator and
measuring the CO/CO
₂
content and gas
flow in domestic hot water mode
1.
The following steps are only required if calibration and
measurement in heating mode (
→
Page 31) could not
be completed successfully.
2.
If required, open all of the draw-off points.
3.
Set the domestic hot water temperature at the heat
generator to the maximum.
Danger!
Risk of burns and scalding!
There is a risk of scalding at the domestic hot
water draw-off points if the water temperature
is set to the maximum.
▶
Avoid contact with the water that escapes
from the domestic hot water draw-off
point.
4.
Open check programme
P.01
.
◁
The heat generator starts in domestic hot water
mode.
◁
The heat generator first switches between status
S.11
and status
S.13
.
◁
The heat generator switches to status
S.93
after
approximately two minutes for calibration.
◁
Do not measure the CO/CO
₂
content or the gas
flow during calibration (status
S.93
).
5.
If the heat generator switches from status
S.93
to
status
S.14
after approximately five to six minutes,
calibration at maximum heat input is complete.
6.
In the next few minutes, measure the CO/CO
₂
content
and the gas flow at maximum load.
7.
Use
to end check programme
P.01
.
8.
Open check programme
P.02
.
◁
If the heat generator permanently switches from
status
S.93
to status
S.14
after five to six minutes,
calibration at minimum load is complete.
9.
In the next few minutes, measure the CO/CO
₂
content
and the gas flow at minimum heat input.
10.
Use
to end check programme
P.02
.
◁
Measurement and calibration in domestic hot water
mode are complete.
9.16
Checking leak-tightness
▶
Check the gas pipe, the heating circuit and the hot water
circuit for leak-tightness.
▶
Check that the air/flue pipe has been installed correctly.
Condition
: Room-sealed operation
▶
Check whether the vacuum chamber has been closed
tightly.