Start-up of ETL
4
Start-up of ETL3000 /ETLONE
Once the ETL station has been mounted outdoor on a pole or
on a wall, follow the start-up procedures:
1)
connection to mains power (optionally, if specified, to 12V
DC)
2)
Check that the earth cable is connected to external door.
3)
Switch on the ETL3000 /ETLONE.
4)
Check that the display shows the correct time and that the
clock is correctly updated.
5)
Check that the measurements of Air temperature and
relative humidity are coherent with environmental conditions. It should not be displayed
values as -50.0 and 0.0
6)
Check that the values on display are coherent with
the datasheet (i.e. not values with a lot of figures)
.
NOTE
:
We recommend to consider the following precautions at chapter 4.1 for a correct
working of the SENS-IT sensors.
ORION S.r.l.
ETL_Operation and Service manual_ 02_17.docx
Pag. 22/35