Wiring in - Underground gland and conduit
Conduit installation
Prepare conduit and wiring as per
section: Site preparation - Underground
wiring, conduit.
Remove the M50 cable gland from the
input plate, keeping the lock nut.
Fit the provided 50mm conduit fitting and
seal over the input wiring and glue to the
50mm conduit with an appropriate
sealant to ensure IP65.
Feed the wiring and conduit fitting
through the 50mm gland plate hole, and
secure the conduit fitting to the gland
plate with the lock nut.
If using auxiliary wiring in the conduit,
repeat these steps with the fitted M25
gland and 25mm conduit fitting and seal.
Ensure 470mm of internal auxiliary wire
from the gland plate.
Provided
Seals
Sealant
area
HP Input +
Grounding
470mm
auxiliary
field
wire
M50
conduit
M25
conduit
Gland installation
Prepare conduit and wiring as per
section: Site preparation - Underground
wiring, cable gland.
Loosen the M50 cable gland, and feed
the HP input wiring and grounding wire
through. Ensure the wiring sheath is
sitting above the gland plate. Tighten the
cable gland and pull on the wiring to
ensure it will not slip.
CRITICAL
If using an auxiliary field wire, the wire
must be a single multi-conductor cable
Ø10 - 14mm to suit the M25 cable gland.
If the auxiliary wire is smaller than Ø10,
the conduit installation must be used.
Loosen the M25 cable gland, and feed
the auxiliary field wire through. Ensure
470mm of internal auxiliary wire from the
gland plate. Tighten the cable gland and
pull on the wire to ensure it will not slip.
M50
cable
gland
M25
cable
gland
HP Input +
Grounding
470mm
auxiliary
field
wire