12
Place a rigid rubber band between the base of the machine and the support surface.
Verify that the support surface withstands the weight of the unit.
Provide a supporting slab of proportional dimensions with the unit if resting on unstable
ground.
The slab must be horizontal and able to withstand approximately 200% of the operating
weight of the machine.
If necessary, use shock absorbers (rubber or spring).
3.4
Verifying clearances (clearance area)
L1
0
L2
800
W1
300
W2
300
L1
500
L2
500
W1
800
W2
500
•
Installation, in addition to the indicated spaces, must enable access to the authorised
personnel for maintenance operations and must take into account the safety distances from
any other equipment installed near the machine.