38
G2020 Series UPS Installation and Operation Manual
– 94861-004
5
INSTALLATION AND OPERATION
5.1
TRANSPORTATION AND INSTALLATION
Transport with forklift. If carry by overhead crane, use four eyebolts (Not provided)
Table 5-1 Transport by Overhead Crane
Model
UPS Cabinet
Landing Cabinet *
500kVA
4 x M20 Lifting Eyes
4 x M16 Lifting Eyes
750kVA
4 x M24 Lifting Eyes
4 x M16 Lifting Eyes
* Use lifting eyes on landing cabinet only to lift landing cabinet by itself, not as part of assembled unit.
Install the unit using the four pre-drilled holes in the UPS channel base. Anchor the unit using appropriate hardware. (Not
provided).
Do not transport UPS cabinet laid horizontally.
Cabinets must be maintained upright within ± 15
°
of the vertical during handling.
5.2
INSTALLATION PROCEDURE
A) Note the load tolerance of the floor
Refer to Table 5-2 for list of UPS weights.
Table 5-2 List of UPS Weights
UPS Capacity (kVA)
500
750
Weight (lb.)
2,756
3,990
B) Minimum clearance required for ventilation
Right side
1 in. (25 mm) (not required when sidecars are used)
Left side
1 in. (25 mm) (not required when sidecars are used)
Back side
0.0 in. (0 mm)
Top side
24 in. (610 mm) (for air flow)
C) Space requirement for routine maintenance
Allow for the following space at the time of installation.
Front
40 in. (1016 mm)
Sides
0.0 in. (0 mm)
Back side
0.0 in. (0 mm)
Top side
20 in. (500 mm)
PROHIBIT
!
NOTE