6 Using the product
65
5.
Start measurement:
[
]
- The stabilisation phase (minimum 2 min) progresses. After this
the measuring phase starts automatically (minimum 5 min).
The stabilisation phase can be interrupted early.
> Press
[Next]
.
- The measuring phase starts automatically.
-
The measuring result is displayed after the measuring phase
has been completed.
Options:
>
[Options]
→
Clipboard:
Data are saved to the clipboard.
>
[Options]
→
Delete clipboard:
Data in the clipboard are
deleted.
>
[Options]
→
Save:
The readings are saved in a record.
>
[Options]
→
Show Graphic:
The readings are displayed in
form of a line graph.
>
[Options]
→
Configure Graphic:
The measurement
parameters to be represented (max. 4) can be displayed (
) or
hidden (
) werden.
>
[Option]
→
Measurement view:
(This function is not available
during a measurement): The readings display menu is opened.
6.2.17.
Gas pipe tests
Calling up the function:
>
[ ]
→
Measurements
→
[OK]
→
Gas Pipe Tests
→
[OK]
.
6.2.17.1.
Tightness test 1
Leak test on gas pipes acc. to DVGW-TRGI 2008
worksheet G600
The leak test (using air or inert gas, e.g. CO2 or N2) is used
for acceptance testing of newly routed or remedied pipes.
The test is performed at the pipe, including the fittings,
without gas installations and corresponding control and
safety equipment. For this test the line must be pressurised
with 150 mbar, whereby this pressure must remain constant
for 10 minutes.
This applies to lines < 100 l. For larger line volumes, the
stability time and measurement period should be adjusted
in accordance with DVGW-TRGI 2008 worksheet G600.
> Connect the connecting plug of the hose pressure connection
set (0554 1203) to the pressure test set (0554 1213), plug the