Page 64 • MN06201 ║ Issue/Rev. 0.1 (2/20)
AccuLoad IV Installation and Maintenance Manual
Completing the Installation
Figure 43.
Flame path verification
Feeler gauge test of cover flame path joint, inspect joint around the complete perimeter
using a 0.0015" (0.0381 mm) feeler gauge. (ALIV-QT shown - use the same procedure
for ALIV-ST).
12.2. Sealing
Each of the AccuLoad enclosures can be sealed using standard seal wires. On the
AccuLoad ST and QT models the seal wire is threaded through holes in two cover bolts
as shown in the following figures:
Figure 44.
AccuLoad ST sealing
Seal Wire
Cross
drilled
bolts
Standard
bolts
AccuLoad ST sealing
Содержание ALIV-QT-XP
Страница 8: ...Page 8 MN06201 Issue Rev 0 1 2 20 Page intentionally left blank ...
Страница 12: ...Page 12 MN06201 Issue Rev 0 1 2 20 Page intentionally left blank ...
Страница 16: ...Page 16 MN06201 Issue Rev 0 1 2 20 Page intentionally left blank ...
Страница 62: ...Page 62 MN06201 Issue Rev 0 1 2 20 Page intentionally left blank ...
Страница 66: ...Page 66 MN06201 Issue Rev 0 1 2 20 Page intentionally left blank ...