Solo Innova Instructions 1-800-782-9927 Version 01-18
Tarm Biomass · 4 Britton Lane · Lyme, NH 03768
Boiler Installation & Start-up > Setting the Boiler
Page 23
26
27
Install Lo-Limit
Probe Use Right
Wire Channel to
Hide Tubing
Install 3 Control Panel Sensors into
Port #23. Make sure they are pushed all
the way to bottom.
28
29
30
Install Sensor and ½”Well for Overheat
Aquastat into Port #27.
Install Insulation on back of top panel.
Install Cover Plate