Solo Innova Instructions 1-800-782-9927 Version 01-18
Tarm Biomass · 4 Britton Lane · Lyme, NH 03768
3.3.3 Temporary Storage
If the boiler installation is going to take place at a later date the boiler and components need to be
stored in a safe, dust-free, dry location.
Moisture can damage the insulation, electrical components, and ceramics. If boiler is subjected to this
kind of environment, it could void the warranty.
3.3.4 Moving the Boiler
See
Section 6.3
Specification Data for weights and measurements of the Solo Innova boiler.
The
boiler is heavy and large!
Moving the boiler into place requires planning and resources. The boiler
may be unloaded using a pallet jack or forklift. Alternately, it can be lifted from above by utilizing the
lifting rings welded to the top of the boiler.
3.3.5 Boiler Set-up
After the packaging is removed and the boiler is set into place, it should be checked to assure that it is
level and securely placed. Loose parts and accessories shipped with the boiler should be removed and
stored in a safe place. A copy of this manual is shipped with the boiler for reference during installa-
tion. The boiler can be set using leveling bolts located on each corner.
It is not necessary to remove the wooded shipping braces and wedges located within the boiler. They
will burn away within a few hours of initial firing.
Before assembling the insulated jacket, determine which side of the boiler will be most convenient for
mounting the pressure relief valve. Remove the appropriate jacket knockouts as shown on
Fig. 3.3.
Boiler Installation & Start-up > Setting the Boiler
Page 16
Fig 3.3 Pressure Relief Valve Knockout
Located on Right or Left Side