8 Commissioning protocol
Company:
Responsible:
8.1 General
Customer:
Date:
Installation:
Object/unit:
Item no:
Installation address:
Model/size
Serial no:
Designation:
8.2 Installation control
Moment
Done
Note
Control report cooling concerning installation
established. (Application shall in some cases be
done, see chapter 3, Refrigerant Control/Reporting).
All unit parts undamaged.
Installation carried out according to instructions (see
chapter 6.4.1, Assembly the Topvex SoftCooler and
chapter 6.4.1.1, Duct connections).
Exhaust sensor ”EHS” moved (see chapter 6.4.2,
Electrical connection).
Condensation drain connected (see chapter 6.4.1.3,
Condensation drain).
Mains supply connected via the Safety switch (see
chapter 6.4.2, Electrical connection).
By-pass damper connected when such is to be used,
accessory (see chapter 6.4.2.1, External/Internal
connections).
Internal operating cable connected (see xchapter
6.4.2.1, External/Internal connections).
The two transparent pressure measuring tubes to
the extract fan connected thru the Topvex SoftCooler
Supply and extract airflow adjusted
8.3 Preparing control unit E28
To receive correct functions the following settings must be done in the control unit E28. Log in into
the control unit E28 (3333) before taking action. As an alternative can the settings be done with the
PC-software tool “Corrigo E-tool Ventilation” then download the configuration file (.vtc) from the Systemair
online catalogue (www.systemair.com).
Installation instructions
208767
18
Systemair Sverige AB