6.4.1.2 Condensation and Heat Insulation
Outdoor air duct and discharge ducts must always be well insulated against condensation. Correct
insulation installation on ducts connected to the unit is especially important. All ducts installed in cold
rooms/areas must be well insulated. Use insulating covering (minimum 100 mm mineral wool) with plastic
diffusion barrier. In areas with extremely low outdoor temperatures during the winter, additional insulation
must be installed. Total insulation thickness must be at least 150 mm.
Caution
• If the unit is installed in a cold place make sure that all joints are covered with insulation, and tape well
• Duct connections/duct ends should be covered during storage and installation
• Do not connect tumble dryers to the ventilation system
6.4.1.3 Condensation drain
Warning
The unit is not to be taken into operation before the included condensation drain and water seal are
connected from the Topvex SoftCooler to the floor drain.
The drain is to be connected to the drain connection under the drip-tray. The drip-tray is located in the
bottom of the Topvex SoftCooler.
Use the included plastic connection pipe which is to be cut to the correct height "H" according to the below
figure. See the below table for the relation of hight "H" and maximum under pressure in the unit.
Fig. 8 Dimension and assembly
H (mm)
Max. Negative pressure (Pa)
85
500
110
1
750
135
1000
1.
Normal conditions
To lead the water from the water seal outlet to the floor drain an extra pipe, not included with the Topvex
SoftCooler, is needed. Connect this pipe and make sure that the slope is at a minimum 1:200 to the floor
drain and also that the complete drain installation are in a frost free space.
Fig. 9 Pipe to floor drain
Installation instructions
208767
13
Systemair Sverige AB