10
A-96.250.331 / 230320
AMU Powercon
Installation
2.
Installation
2.1. Installation Checklist
Check
Instrument’s specification must conform to your AC power ratings.
Do not turn on power until instructed to do so.
Installation
The transmitter is intended for panel mounting. The dimensions
Dimensions of the AMU Transmitter, p. 11
.
Electrical con
-
nections
Connect all external devices, see
Connect the power cord, but do not switch on power until all exter
-
nal devices are connected.
Power-up
Open sample flow and wait until flow cell is completely filled.
Switch on power.
Adjust sample flow.
Instrument
setup
Program all sensor parameters see
Program the required temperature compensation.
Program all parameters for external devices (interface, recorders,
etc.).
Program all parameters for instrument operation (limits, alarms).
Run-in period
If the conductivity value of the sample is very low, the sensor might
need some time until the correct reading is displayed.