30
20
80
All holes
Ø11
Figure 8
STEP SIX
STEP SEVEN
Carefully lift up one panel and place in holes. Secure with temporary
supports. Repeat this operation for the other panel. If you have not
already done so place a bearer (e.g. an old brick) in the bottom of
each hole to prevent the posts penetrating through the soil. Place
a 55mm channel on top of the corner posts at the rear of the shed
with the long leg inward and attach with 10x16 self drilling screws.
Place another 55mm channel on top of the mullions (or corner
posts) at the front of the shed with the long leg inward and attach
with 10x16 self drilling screws. Place a Z rail 2410mm from the top
channel at the rear of the shed with the long leg inward and attach
with two 10 x 16 self drilling screws. Ensure the Z rail is level with
the Z rails previously installed. Lift a C section rafter into place and
temporarily support while ensuring the top is 30mm higher than
the top of the SHS. This provides the correct height for the slope
of the roof sheets. Fix the C section rafter to each SHS using two
M10 x 65 bolts at 80mm centres with the first bolt 20mm from the
top of the SHS, ensure two washers are used. Repeat for other C
section rafter.
Layout the second side panel and repeat step four and five.