ROLLER DOOR
DOUBLE PA DOOR OPTION
DOWNPIPE INSTALLATION
Figure 48
Figure 49
Figure 50
Figure 51
Install roller door/s, refer to manufacturers specifications and
installation instructions.
If you have chosen the double door option for your Homeshed
there will be one less wall sheet and the Z section door stop and
infill will measure 1545mm. Included with the extra P.A. door is a
seam flashing. Locate your position for the P.A. doors, the example
provided is for a double door hung 1 sheet from left post (Figure
50). The space for the P.A. door can be created by half lapping
one sheet over another full sheet. To eliminate cutting sheets
it is recommended you temporarily locate both jambs in their
approximate positions. Then lay the wall sheets on the ground
lining up all sheets with the intended position of the P.A. doors.
Proceed to install the wall sheets from the corner post working
toward the first door jamb (Figure 51). Refer lapping detail (Figure
65). Secure sheets with one rivet per crest at the top, two rivets per
pan at the base and one rivet mid-span at the join between sheets
(Figure 28). The Z rail base should be temporarily supported during
this step. Repeat procedure working back from opposite corner
post, you may need to stretch sheets slightly to fit.
Cut the downpipes to the required length, allow room for any
downpipe shoes or other optional fittings. Place the downpipe over
the downpipe outlet and attach with two rivets through both sides
of the downpipe (Figure 48). Seal with silicone.
Place the downpipe bracket as close to the ground as possible. Fix
the bracket using downpipe rivets (Figure 49). Seal with silicone.
Содержание Flat Roof Homesheds
Страница 22: ...NOTES...