STEP NINETEEN

Figure 40

Figure 41

Refer to the Gutter Installation section of the instructions before 
completing Step 19. Make a mark mid-span on the top of the first 
crest of the roof and position the barge flashing so the end is 
minimum 5mm past the mark. Fix with two 10x16 screws (Figure 
40). Position the  other barge flashing so the ends overlap by 
minimum 10mm. Fix two more 10x16 screws into top channel 

(Figure 41). Fix a 10x16 screw mid-span so that it penetrates both 
barge flashings and the top channel. Fix a 10x16 screw mid-span so 
that it penetrates both barge flashings and the first crest of the roof 
sheet. Fix two more 10x16 screws at either end again penetrating 
the crest of the roof sheet (Figure 41). Repeat the procedure for the 
opposite side.

Содержание Flat Roof Homesheds

Страница 1: ...at Roof Homeshed Read these instructions thoroughly before starting your project and refer to them constantly during each stage of construction Contact Stratco for advice if you do not have the necess...

Страница 2: ...Gutter End PA Door Infill Roller Door Infill SHS Post VF Gutter Door Infill Bracket Front Centre Mullion Front Side Mullion PA Door Jamb 55mm Back Channel Barge Flashing Bridging C Section Z Section D...

Страница 3: ...100 x 50 POP Downpipe Strap Universal Deck Strap PA Door Handle Self Drilling Screw Rivet Nut and Bolt Wafer Head Screw PA Door Prodek...

Страница 4: ...irm natural sandy soil Place a bearer e g an old brick in the bottom of each hole to prevent the posts penetrating the soil Check locations of holes before proceeding to the next step CODE DESCRIPTION...

Страница 5: ...ch end Silicone Sealer Run a bead of silicone along one of the 55mm corner channels 3000mm long for 2400 high and 3300mm for 2700 high shed making sure the bead is on the short leg Place against the b...

Страница 6: ...l to Z rail is 2410mm for 2400 high shed and 2710 for 2700 high shed Refer Figure 7 Refer fixing details on the back page Mullion may be replaced by corner post as per shed type Mullion may be replace...

Страница 7: ...ront of the shed with the long leg inward and attach with 10x16 self drilling screws Place a Z rail 2410mm from the top channel at the rear of the shed with the long leg inward and attach with two 10...

Страница 8: ...e top 55mm channel Figure 12 FRONT VIEW 65 bolts attach the 50 x 50 x 1 6mm SHS to the top 55mm channel and bottom Z rail ensure two washers are used Figure 10 11 CODE DESCRIPTION A G36 UNIVERSAL n a...

Страница 9: ...oller door bracket s before completing this step Install the mullion flashings to the mullion ensure the flashing is flush against the 55mm top channel Figure 14 Using rivets attach the flashing to th...

Страница 10: ...nspect all connections and all members for squareness and levels Once you are satisfied proceed to place concrete around all posts Use temporary bracing to maintain squareness while concrete sets Chec...

Страница 11: ...ach the flashing to the mullion 100mm from the top and bottom and mid height both sides Figure 20 Using three rivets install the infill bracket to the mullion mullion flashing should be attached Figur...

Страница 12: ...t the top two rivets per pan at the base and one rivet mid span at the join between sheets Figure 28 Locate your position for the P A door the example provided is for a left hand hung door 1 sheets fr...

Страница 13: ...P A door to ensure there is enough room to open and close the door Install remaining door jamb using a 10x16 screw attached to the top channel and a rivet attached to the bottom Z rail Figure 29 With...

Страница 14: ...osition the corner post flashing ensuring the bottom edge is sitting on top of the bottom Z rail Figure 34 Trim the top of the corner post flashing as required Figure 36 Secure flashing with rivets at...

Страница 15: ...on the C section rafter Start laying the sheets from the outside edge of the top channel on the long side Installing one sheet at a time ensuring sheet overhang is even at each end fix using one 10x1...

Страница 16: ...crews Figure 40 Position the other barge flashing so the ends overlap by minimum 10mm Fix two more 10x16 screws into top channel Figure 41 Fix a 10x16 screw mid span so that it penetrates both barge f...

Страница 17: ...ter Bend the tab back over itself Figure 44 Repeat for the other end and evenly space with a maximum spacing of 1200mm Figure 45 Attach gutter to top rail with rivets Figure 45 Repeat for opposite gut...

Страница 18: ...Then lay the wall sheets on the ground lining up all sheets with the intended position of the P A doors Proceed to install the wall sheets from the corner post working toward the first door jamb Figu...

Страница 19: ...centres start 100mm from end Remeasure the door jambs and adjust if necessary Figure 50 Install the door jamb from which the door will be hung using a 10x16 self drilling screw attached to the top ch...

Страница 20: ...sheet loosely into position and check to see that the window will fit the opening Figure 58 Ensure the wall sheets either side of the window tightly abutt the frame so no gaps occur Correct spacing of...

Страница 21: ...curing the window frame to the crests of the wall sheet top and bottom and evenly space rivets either side Figure 63 Place a bead of silicone in each corner of the window to prevent water entry the re...

Страница 22: ...NOTES...

Страница 23: ...SHEETS Your Stratco Flat Roof Homeshed will maintain its good looks for even longer with a simple wash and wipe down Cleaning should be performed as often as is required to remove any dirt salt and po...