Installation
EN
751.792 | Z01 | 1504
11
5.
Connect the minus cable M- with the correct polarity to the
solar module terminal pair on the solar charge controller.
6.
Remove the covering from the solar module.
When the solar module is correctly connected, LED 2 lights up
green (permanently or alternating between bright/dark).
Connecting loads
Loads that must not be deactivated by the solar charge
controller deep discharge protection, e.g. emergency lights or
radio connection, can be connected directly to the battery and
separately fused.
1.
Ensure that the loads are switched off and the corresponding
fuses are removed.
2.
Label the load connection cables as a plus cable (L+) and a
minus cable (L
–
).
3.
Lay the load connection cables parallel to each other
between the solar charge controller and the loads, but do not
yet connect them.
4.
First connect the L+ load cable with the correct polarity to
the right pair of terminals on the solar charge controller (with
the lamp symbol).
5.
Then connect the L- load cable with the correct polarity to
the right pair of terminals on the solar charge controller (with
the lamp symbol).
6.
Replace any removed fuses and then switch on the loads.
When the loads are correctly connected, LED 4 remains lit in
green or yellow.
Step 3 Completion work
1.
Secure all cables in the immediate vicinity of the solar charge
controller using strain relief fittings (clearance of approx.
10 cm).
2.
Check the LED displays.
The solar charge controller is ready for operation.
Содержание Solarix 2020-x2