NOTICE!
–
Between the data connection cables (RS485/
Ethernet/Modbus RTU) and the DC/AC lines,
maintain a distance of 200 mm, to avoid
interference in the data transmission.
–
The protection class IP65 for type coolcept
3
-
x is only ensured if the AC and DC plugs are
plugged in and the RJ45 sockets are sealed
with sealing caps.
1.
If necessary, establish the data connection:
n
Connect the inverters and the master with data connec-
tion cables.
n
Plug a suitable termination plug into the last inverter.
2.
Seal open RJ45 sockets of coolcept
3
-x with sealing caps.
3.
Forcefully press the plug connector mating piece (DC cable)
into the DC connection on the inverter until it audibly locks in
place.
4.
Plug the AC connector onto the coupling on the inverter, until
the plug audibly locks in place.
5.
Switch on the AC miniature circuit breaker. The start page for
1st commissioning is shown on the display.
6.
Perform 1st commissioning and switch on the DC supply, as
described in
4.7 Initial commissioning of the inverter
4.7.1 Function
Initial commissioning starts automatically when at least the AC con-
nector has been installed and switched on as described previously. If
initial commissioning is not fully completed then it starts again anew
the next time the device is switched on.
Initial commissioning is a guided procedure that sets the following
information:
n
Display language
n
Date / Time
n
Country
n
Reactive power characteristic curve (if prescribed for the
selected country)
The following applies when setting the country:
Conditions for starting
initial commissioning
Guided initial commis-
sioning
Setting the country
EN
750.661 | Z03 | 2016-09-12
35