Commissioning the Installation
SolarEdge Installation Guide – MAN-01-00002-1.6
59
Continue to hold for five seconds more and you will see this screen:
P a i r i n g
T u r n S w i t c h T o O n
2
Turn on the inverter ON/OFF switch at the bottom of the inverter within five
seconds. If you do not turn ON the inverter ON/OFF switch within five
seconds, the inverter then exits pairing mode.
The following screen is then displayed indicating that the inverter is
performing the process of pairing and is assigning power optimizers to the
inverter.
P a i r i n g
R e m a i n i n g [ S e c ] : 1 0 4
This message displays a countdown of the seconds until it completes the
pairing process. If pairing fails, an error is displayed. This error appears only
if the above steps were not followed. If an error appears, then follow the
pairing steps again.
After commissioning succeeds, the following message is displayed:
P a i r i n g
P a i r i n g C o m p l e t e d
3
Since at this stage the ON/OFF switch at the bottom of the inverter is ON, the
power optimizers start producing power and the inverter starts converting
AC.
WARNING!
After you turn ON the ON/OFF switch of the Single Phase Inverter, the DC
cables carry a high voltage and the power optimizers no longer output a safe
1V output.
Après avoir mis l'interrupteur ON/OFF de l'onduleur monophasé sur ON, les
câbles DC portent une haute tension et les optimiseurs de puissance ne
génèrent plus la tension de sécurité de 1V.
Содержание OP250-LV
Страница 1: ......
Страница 94: ...Inverter User Interface SolarEdge Installation Guide MAN 01 00002 1 6 94...
Страница 122: ...Limited Product Warranty SolarEdge Installation Guide MAN 01 00002 1 6 122...