45
December 2020
|
Solar Stik
®
, Inc.
SYSTEM SETUP AND OPERATION GUIDE FOR THE SOLAR STIK USAF G-BOSS MEDIUM AND HEAVY HYBRID POWER SYSTEM
PRELIMINARY DRAFT
Set Start Gen
Volts = 18.0-31.8
Set Start Volts
Delay=0 sec-127 min
Set Stop Gen
Volts = 28.8
Set Stop Volts
Delay = 1 Min
continued
SETUP
04A Gen Run VDC
Press Select
Status
04 AGS Setup
Set Start Gen
Volts = 25.6
Set Start Volts
Delay = 15 sec
Set Stop Gen
Volts = 18.0-32.0, Float
Set Stop Volts
Delay=0 sec-127 min
Set Gen Run Time
Volts = OFF
Set Start Gen
Hour=1:00A
Set Start Gen
Minute= 00:45A
Set Start Gen
AM-PM= 00:00A
04B Gen Run Time
Press Select
Set Gen Run Time
Volts = ON
Set Start Gen
Hour = 12:00P
Set Start Gen
Minute= 00:00A
Set Start Gen
AM-PM= 00:00A
Default=OFF
Set Stop Gen
Hour= 1:00P
Set Stop Gen
Minute= 00:45P
Set Stop Gen
AM-PM= 00:00P
Set Stop Gen
Hour= 12:00P
Set Stop Gen
Minute= 00:00P
Set Stop Gen
AM-PM= 00:00P
Set Start Gen AC
Amps = OFF
Set Start Amps
Delay=0 sec-127 min
04C Gen Run Amps
Press Select
Set Stop Gen AC
Amps = 18.0-32.0
Set Stop Amps
Delay=0 sec-127 min
Default=OFF
Set Stop Gen AC
SOC = 21-100%
04D Gen Run SOC
Press Select
Set Start Gen AC
SOC = 20-99%
Default=OFF
AGS Function Notes
• After 15 seconds at or below 25.0 V, the PRO-Verter sends the
start signal to the Generator.
• After 1 minute at or above 28.8, the PRO-Verter turns off the
Generator.
• If the Generator does not start and the battery voltage gets
down to 24.4V (LBCO), the AC Out (Inverter) turns off. This is the
LBCO voltage in the menu tree.
SETUP Button Menus continued
Setup: 04 AGS Setup