10 COMMISSIONING
Before operation, the following checking should be carried out:
1) Check and ensure all the connections are correct and wires diameter is suitable.
2) Ensure that the controller DC power has fuse; battery positive and negative have
correctly connected.
3) Emergence stop input must be connected to positive of starting battery via normally
close contact of emergency stop.
4) Take proper actions to prevent engine to disconnect crank (e. g. Remove the
connections of fuel value). If checking is OK, connect start battery, select Manual
Mode, controller will execute the program.
5) Set controller as Manual M
ode, press “start” button
to start genset. If failed within the
setting crank times, controller will send
“
Failed to Start
”
signal
; then press “
stop
” to
reset controller.
6) Recover actions of preventing engine to disconnect crank (e. g. Connect wire of fuel
value), press
“start”
button again, genset will start. If everything goes well, genset will
normal run after idle running (if configured). During this period
, watch for engine’s
running situations and voltage and frequency of alternator. If there is abnormal, stop
genset and check all connections according to this manual.
7) Select the Auto Mode from front panel, connect to mains signal. After the mains
normal delay, controller will transfer ATS (if configured) into mains load. After cooling,
controller will stop genset and into standby state until mains abnormal again.
8) When mains abnormal again, genset will start automatically and into normal running,
send signal to make gens close, transfer ATS and make genset take load. If it not
likes this, please check connections of ATS according to this manual.
9) If there are any other q
uestions, please contact Smartgen’s
service.