Page 38
6)
Go to the Operator Panel (page 44) and verify that the red LED labeled “Main
Power” is lighted. Before proceeding to start the power up sequence of Cycraft,
operators should familiarize themselves with the switches and controls on the
Operator Panel.
5.11 POST INSTALLATION TESTING AND INSPECTION
After the mechanical and electrical installation is complete, it is necessary to carry out
a final checking procedure and make some adjustments if necessary. To carry out
the final tests and adjustments, you must power UP Cycraft.
Carry out the Power-UP sequence according the procedure outlined in section 6.2.
Before you power-up Cycraft, make sure of the following:
(a) The power cord is connected to the correct voltage outlet and the green main
power LED is lighted.
(b) The emergency power off switch and motion stop switch (behind the coin chute
box) are released.
Make sure there are no personnel or objects under or in the area of the cabin
before switching the power on. The power up sequence will move the cabin
and personnel can be injured.
Make sure there are no passengers in the cabin when power is turned on.
The extra weight of the passenger can cause a fault in the power ON
sequence.
After successful power UP, it is possible that a beeping sound is heard and the red
LED labeled “Safety Sensor” on the Operator Panel is lighted. This indicates that
adjustments on the safety sensors (floor sensor and/or photo sensors) are needed.
Even if the beeping sound is not made, read the following sections and verify that the
sensors are in the best operating conditions.
Содержание Cycraft
Страница 16: ...Page 16 3 NAMES OF MAJOR PARTS 18 11 12 13 14 15 16 17 28 ...
Страница 30: ...Page 30 Hexa bolt M8 x 30L DU Bush 10 15 Rubber Washer 11 20 3t Spring Washer Flat Washer ...
Страница 73: ...Page 73 10 2 Cabin Schematic SCHEMATIC 2 HERE ...
Страница 74: ...Page 74 10 3 MCU Schematic DOCUMENT END SCHEMATIC 3 HERE ...