Work step
Done
4.4
If applicable, document and report damage, deviations and missing components
4.5
Acknowledgment and confirmation by carrier
5
Transport to base area and prepare for setup
5.1
Transport to the base area
If crane: Mount crane lugs
5.2
Remove cable gland plates
6
Set up the charging station
6.1
If applicable, Mount crane lugs and fasten the hoisting gear
6.2
Loosen screw connection with load carrier
6.3
Lift charging station from load carrier and position it over base area
6.4
Introduce cables and wires and lower the charging station
6.5
Fasten the charging station to the base area, tightening torque according to bolt anchor used
6.6
Drill holes in the cable gland plate and insert cable glands, take Ethernet cable into considera-
tion, if applicable
6.7
Insert and screw in cable gland plate, tightening torque: 4 Nm, seal cable gland plate, if applica-
ble
6.8
If dispenser: Repeat work steps on the back of the charging station, take comm., control and
auxiliary cables into consideration
6.9
Install baseboards
6.10
Install roof
7
Connect the charging station
7.1
Finally cut conductor of the power supply cable to length and apply M10 cable lug
7.2
Connect conductor to copper bars, tightening torque: 40 Nm, mark with pen
7.3
Protective cover in front of circuit breaker installed again
7.4
Ethernet cable for CPO connected to right-hand port
7.5
If dispenser: Finally, cut DC cable to length and apply M10 cable lug, connect to DC busbars,
tightening torque 40 Nm and mark with pen
7.6
If dispenser: Connect communication, control and auxiliary cables
7.7
Insert filter box, ground and install filter cover
8
Commissioning
8.1
Check consistency and low impedance of protective conductor
Check insulation resistances
8.2
Check whether all circuit breakers (automation area), circuit breakers (AC input area), residual
current devices (door) are switched on
8.3
Close/lock device doors
8.4
Switch on via upstream switching device
8.5
Check for correct power-up
8.6
Check function of the Emergency Stop switch