Decommissioning
⚠
DANGER
Danger from dangerous voltages
Death, severe injuries and property damage
•
Only trained, instructed electricians are allowed to take the control out of operation.
•
All safety instructions in section „"Safety instructions" (
11)“ as well as locally ap-
plicable regulations must be observed.
•
It must be noted that other system parts can lead to tension or automatic processes
are running. Only take commissioning when the system is switched off or in a seg-
ment of the system that is switched off.
•
Note there may be dangerous stored charges on the terminals. Wait five minutes af-
ter switching off the control system voltage before carrying out any further activities.
Procedure
•
De-energize the system or part of the system in which the control is located.
•
Secure against being switched on again.
•
Wait five minutes until the stored charges have completely dissipated.
•
Disconnect all connections.
•
Loosen the control fastening and remove it from the bracket.