myGrid Shutdown Procedure
Step
Action
Result
1
Press and hold ON button.
Output Mode indicator is now OFF - Inverter is
Idle and will not export or provide any backup
supply.
Charging Mode, Battery and Alarm indicators
will remain On.
Grid (if present) will continue to feed through to
AC Load.
2
Solar Isolating Main switch
Switch OFF by pressing levers down.
Solar is now isolated from system.
3
Main Battery Circuit Breaker (under cover)
Push handle firmly down into the Off ( 0 ) position.
4
Pre-charge / Battery Sense Isolator switch (under
cover)
Switch OFF by pressing levers down
Inverter is now isolated from battery bank.
Charging Mode, Battery and Alarm indicators
will turn OFF.
5
Switch OFF AC Isolator(s)
– Source and Load
AC Source, Transfer and AC Load indicators
are now OFF. No supply to AC Load.
Inverter is now isolated from grid supply.
Start up Procedure
– Perform opposite action in reverse from 5 to 1.
Shutdown Procedure