myGrid
Installation Notes
F
IT
T
OP
C
OVERS
Locate the Top Cover on the frames so that it overhangs at the rear and the front of the cover
is resting on the front edges of the frames as shown in Figure 11a.
Move the cover towards the front of the frames to engage the pins on the inside rear of the
cover into the inserts in the frames.
Figure 11a
Figure 11b
Lower the cover and secure it to the frames using M6 x 16mm long screws (2 off). Refer to
Figure 11b.
Position Battery Enclosure
Battery enclosure is now suitably assembled to be positioned. The battery enclosure (once
fitted with batteries) is quite heavy and must be placed on a solid surface - if to be placed on
dirt then using concrete squares for each leg is suitable. Ensure all legs are supported upon a
solid surface and the battery enclosure is level (use a spirit level to ensure battery enclosure is
level side to side and front to back).
Adequate ventilation is required. Air is drawn in from below each side panel and vented out at
the top of the front side panel.
Batteries are degraded by high temperature. Enclosure is to be placed in coolest position and
MUST be protected from direct sunlight.
Cable entry is provided at the rear of the DC Switchbox. Position the battery enclosure to
minimise cable length to the SP PRO or SP PRO GO via most appropriate cable entry point