HeBel inStallation
*important* releasing glass door
prior to continuing with installation ensure you release the
glass door. first remove pins located on either side of the unit,
then proceed to slowly lower the door from its factory position.
you should now be able to open and close the door.
step 4: steel frame
Construct a steel frame (minimum 51mm thick) on either side
of the enclosure. please allow for a 25mm air gap all the way
around the appliance.
**important**
it is strongly recommended that the steel frame be constructed
with a minimum distance of 300mm below the ceiling, this
allows the cavity lid to be placed directly above and prevents
heat from traveling above the lid via the frame.
step 7: steel frame Continued
For structural support construct a steel frame (minimum
51mm thick) on the back wall and connect to the two side steel
frames, remembering to leave a 25mm air gap to all sides of
the appliance.
step 6: positioning of the unit
Place the firebox into position on top of the sheet metal.
Remember to leave a 25mm air gap on all sides of the firebox.
if the unit is to be installed without legs.
**iMPortant**
Please refer to opening lower vents in the preliminary install
section.
step 5: assembly of legs
if your installation requires the unit be elevated install the
appliance legs at this stage, ensure the legs are adjusted and
fixed at this stage.
**iMPortant**
Please refer to appliance legs installation in the preliminary
install section.
Содержание epi950
Страница 5: ...5 ...
Страница 50: ...50 ...
Страница 56: ...56 1300 851 304 info sculptfireplaces com au PO Box 1232 Mornington VIC 3931 Edition 25 05 17 ...