SAMES KREMLIN
Page 8
Manual : 573.190.112
MATERIAL PRIMING (STAGE 1)
Move the valve (20) hand lever to supply the
pump with material A (BASE).
Move the valve (11) hand lever horizontally.
Connect the air tube on the hole on the far left
of the plate (
⇒
opening of the CTM valve to
the container B).
Screw the black regulator until pump begins
to start up (pressure : from 1 to 2 bar / from
14.5 to 29 psi).
The base A is drawn then delivered by the
BASE fluid section. It passes through the
valve (11) of the manifold and goes back to
the container A.
The catalyst flows from container B, is drawn
by the CATA fluid section. It passes through
the valve (12) of the manifold and goes back
to the container B.
Leave the materials circulate for a few
minutes. When air bubbles are evacuated,
the priming is over.
B
S
A
1
20
11
12
WORKING (STAGE 2)
Leave the valve (20) hand lever in the same
position (the pump must be supplied with
materials A and B).
Position the valve (11) hand lever vertically.
Connect the air tube on the hole on the far
right of the plate (
⇒
opening of the CTM
valve towards the AR valve).
Screw the black regulator 'Pump pressure'
until the pump begins to start up.
The base A and the cata B are drawn then
delivered by their respective fluid section.
Each material comes to the manifold and is
mixed at the outlet in the mixer.
Point and trigger the gun into a waste
receptacle.
When material flows out regularly, screw the
phosphorous regulator "Spraying air".
Adjust the 2 regulators to get a correct fan :
- adjust the material pressure with the black
regulator,
-
adjust the spraying air with the
phosphorous regulator.
B
S
A
20
11
12
2