57
Adjust the cables
1. Drive a vehicle with a total weight of 2000 kg
centered onto the main lift. Make sure that the
vehicle is also centered laterally on both run-
ways.
2. Push the Up button until all cables are tensioned
and the acoustic alarm switches off.
3. Raise the main lift by around 1 m with the Up
button.
4. Use the threaded sleeves (4) to adjust the cables
(5) on all 4 lift columns so that they are evenly
tensioned.
5. Secure the 4 threaded sleeves at the top with
two M20 lock nut
.
14.Wheel alignment kit AK/FK/CK..
(optional)
14.1 Supplied parts
AK : Wheel alignment Kit for post lift types
consisting of
•
1050mm slip plate for SM65(50 mm height)
1700mm slip plate for SM40/SM40NB (50 mm
height)
1800mm slip plate for SM40LT( (66 mm height)
1050mm slip plate for SM55(75 mm height)
•
Fixed /end filler plate
•
Moveable filler plate(50mm height)
•
Optional: 2 pcs Turning radius gauge(50mm
height ) for the relevant wheel alignment system
(noly can sit for 500,450,380,350mm width turn table
for alignment lift)
CK: Comfort kit for SM40-47-BMW
consisting of
•
1050,450,200,150,150,100,50mm various
moveable filler plate(50mm height)
•
Optional: 4 pcs Turning radius gauge(50mm
heigh) for the relevant wheel alignment system
FK: Filler kit for SM40/SM40NB/SM65
consisting of
•
1050mm Fixed filler plate
•
Fixed /end filler plate(50mm height)
•
Moveable filler plate (50mm height)
•
Optional: 2 pcs Turning radius gauge(38mm
heigh) and others..
14.2 Assembly
These post lifts can be combined with wheel
alignment systems from different manufacturers.
The post lifts must be converted for use. Thus, on
each runway the base plate at the front and back
must be replaced by filler plates and slip plates
from the wheel alignment kit.
On each side: example for AK on SM65/SM55LT
1. Remove the lifting table ramp (only for SM55LT ).
2. Put the slip plate cover the runway.
3. Secure the slip plate (use the corresponding M10
bolts and washers).
4. Insert the two locking pins ("A“) for each slid
plates.
For SM40-47-BMW lift (Also SM65 lift) ,using the set
screw to leveing the platform on position hole of 2,if
need shim under the platform .then tighten up the screw
on position hole of 1.