2000781K MkII MLB Operating Procedure
Page 64 of 68
17.
LCT Procedure
PSC part
4000637 Lightband Compression Tool (LCT)
can be used to compress the Lightband prior to Stowing.
They are ideal if the satellite weighs less than the total Separation Spring compressive force or during horizontal
integration.
Note, an LCT consists of a single assembly. A pair of LCTs, one on the Lower Ring and one on the Upper Ring,
are required at each location.
17.1 Equipment
Figure 17-1 shows the individual equipment necessary to operate LCTs and also the LCTs installed on the
Lightband. See Table 2-6 for a detailed equipment list.
Figure 17-1: LCT Equipment
A: Lightband Upper Ring flange
B: Lightband Lower Ring flange
C: Ty-Rap ERG 50 cable tie tool
D: LCT Pair with cable tie installed
E: MS 3367-1-0, 7-inch nylon cable ties (before installation)
F: Cable ties (removed after Stowing)
G: Single LCT assembly
H: Primary portion of LCT
I: Attachment screw and washer of LCT
J: Correct LCT attachment points
K: Incorrect LCT attachment points
Содержание PSC MOTORIZED Lightband MKII
Страница 25: ...Copyright PSC 2000781K MkII MLB Operating Procedure Page 25 of 68 Figure 8 1 Stow test circuit 1...
Страница 37: ...Copyright PSC 2000781K MkII MLB Operating Procedure Page 37 of 68 Figure 9 1 SFF test circuit 1...
Страница 46: ...Copyright PSC 2000781K MkII MLB Operating Procedure Page 46 of 68 Figure 10 1 Deploy test circuit 1...