For installations where the unit is mounted directly on the inside of an external wall. 

This installation requires a 2° fall from the heater connection to the wall terminal to 

drain condensate and wind blown rain—the Arriva Direct A and B flue kits have an 

inbuilt 2° fall.

Direct flueing using the Direct A and B flue kits - ARRIVA models only

Before starting, create the wall penetration. The minimum diameter required is 80 mm to non-

combustible surfaces such as brick, and 100 mm to combustible surfaces such as plaster.

Connection

Sleeve

Terminal

Direct flueing - mushroom flue kits

The flue consists of three parts; 

sleeve, inside connections and 

tube, and outside terminal. 

Disassemble by pulling hard on 

the outside terminal and inner 

connections, then pull the sleeve 

off the outer terminal.

1. Disassemble manifold

Fixing Screw

"TOP"

5-10mm

Don't remove green plastic covering from sleeve.

Fix the sleeve to the wall using the 

three screws provided. The flange 

is marked ‘TOP’. The sleeve must 

be fitted with this mark up. Check 

sleeve protrudes 5-10 mm on the 

outside.

4. Fix sleeve

Cut (leave 20mm free)

Pull hard

Fixing tie Lug

Sleeve

Terminal

Pull hard on the LH and RH ties, 

and clip ties over the lugs inside the 

sleeve. You should be able to pull 

the ties two or three slots past the 

starting point. Cut the ties approx. 

20 mm past the lugs and bend so 

they are parallel with the wall.

7. Attach ties

Do not extend beyond red line

Extension joint under plastic

Extension

(A flue only)

Adjust length by turning sleeve

Measure the wall length through 

the drilled hole. Adjust the sleeve 

length to the wall thickness 

plus 5-10 mm (required sleeve 

protrusion from wall).

2. Adjust flue length

Adjust length by turning sleeve.

Extension joint

under plastic

Extension

("A" flue only)

Do not extend

beyond red line

For ‘A’ flues, depending on wall 

thickness, the flue extension may 

need to be removed. There is no 

extension on the ‘B’ flues, they can 

be fully adjusted by turning the 

threaded section.

3. Remove flue extension

Terminal seal

(add weatherboard

seal here)

Check the rubber seal is in place 

on the terminal. For weatherboard 

walls, add the spare rubber seal 

provided to compensate for the 

weatherboard angle.

5. Check and add rubber seal

Label

Fixing tie

Terminal

"TOP" mark "A"

From the outside insert the terminal 

into the sleeve with the ‘A’ mark at 

the top.

The LH fixing tie is marked ‘LEFT’ 

(from the inside)

6. Install terminal

lnner

connections

Screw

Top mark

Push the inner connection 

assembly into the terminal tube. 

Ensure correct positioning—refer 

‘TOP’ mark. Fix with the three 

screws provided.

8. Insert inner connection

Outlet

Rubber cap

Inlet

Adjust the manifold as required. 

The manifold can still be turned 

after attaching.

9. Adjust manifold

Содержание Arriva

Страница 1: ...Arriva and Evolve gas fireplaces Flue installation guide...

Страница 2: ...alled with an approved flue system approved components are shown in this guide Warning Improper installation adjustment alteration service and maintenance can cause property damage personal injury or...

Страница 3: ...wall terminal 21 Connecting the heater exhaust pipe 22 Connecting the air supply 23 Arriva condensate drain kit connection 24 Evolve condensate drain kit connection 25 Appendices Appendix 1 ESBEND 90...

Страница 4: ...direct flue kit available for the Evolve is the ASPDFK The direct mushroom flue kits that can be used for the Arriva are not suitable as the telescopic exhaust section of the Evolve is not long enoug...

Страница 5: ...When considering the location of the fire ensure the flue path is free from obstructions such as noggins wiring joists etc Adaption flue kit Flue pipe ESPIPE900 Wall terminal ESWTERM Vertical in wall...

Страница 6: ...te the o rings on the inner pipes prior to assembly This is important as o rings can dry out and break and replacing o rings is difficult Do not use petroleum based lubricants as these will cause dete...

Страница 7: ...minal at all times DO NOT DO NOT DO NOT DO NOT Do not flue into natural draught flues or fireplaces Do not flue into other rooms Do not flue into roof spaces Do not flue under floor spaces To ensure p...

Страница 8: ...the fire Direct flue kit ASPDFK aluminium Suitable for walls up to 385 mm thick can be cut to length Can also be used with ESPIPE900 for longer flueing The minimum length when measured from the back p...

Страница 9: ...flue installations when used with the adaption flue kit Wall plate ESPLATE Used in down and out flueing to cover the floor penetration and also as an extra wall cover if required to tidy up an install...

Страница 10: ...Socket o ring end of previous component Socket o ring end do not cut Non socket end can be cut Connecting the 45 bends ESBEND If installed incorrectly there is potential for the outer bend to overhea...

Страница 11: ...ue transition When installed as a vertical flue the flue transition is fastened to the rear wall by the wall straps supplied Elbow component of the adaption kit requires 25 mm clearance to combustible...

Страница 12: ...e markings are still useful for indicating the correct position of the flue transition within the enclosure for other flue applications For weatherboard walls drill through the centre of the weatherbo...

Страница 13: ...le to pull the ties two or three slots past the starting point Cut the ties approx 20 mm past the lugs and bend so they are parallel with the wall 7 Attach ties Do not extend beyond red line Extension...

Страница 14: ...penetration The minimum diameter is 80 mm to non combustible surfaces such as brick and 100 mm to combustible surfaces such as plaster Allow for a continuous 2 fall from the fire to the wall terminal...

Страница 15: ...ed using the ESBEND kit 4 Create a vertical roof terminal 5 Secure joints between flue components through the outer pipes with screws and secure the entire flue system using the wall straps supplied 6...

Страница 16: ...casting and the ESPIPE900 The transition component must not be connected directly to the ESPIPE900 which is plastic due to the heat of the flue gases 3 Fit lengths of ESPIPE900 as required Allow for a...

Страница 17: ...to non combustible surfaces such as brick and 100 mm to combustible surfaces such as plaster Allow for a 2 fall back to the heater 2 Create the 90 bend using the ESBEND kit 3 Join the condensate trap...

Страница 18: ...nterior wall Wall plate Stand off clip Interior wall Floor penetration 1 Flue slide stopper provided with the ASPKIT03 EVOKIT03 2 Air hose from unit 3 Condensate trap component acts as a transition pi...

Страница 19: ...900 as required 4 Create the floor penetration ensure the hole edges are smooth The minimum diameter is 80 mm to non combustible surfaces such as brick and 100 mm to combustible surfaces such as plast...

Страница 20: ...e 3 From the new end of the outer pipe measure and mark off an additional 12 mm on the inner pipe Cut the inner pipe at this mark Take care to keep the cut parallel to the outer pipe The additional 12...

Страница 21: ...s shown below Take care to avoid cutting the external wall plate and keep the cuts of the internal and external pipes as parallel as possible Remove all burrs and swarf from the cut ends 3 Align the a...

Страница 22: ...tor groove A red line will show if you have gone too far 3 Adjust the telescopic exhaust pipe to attain the desired position of the heater 4 Fix the telescopic exhaust pipe in place with the flue slid...

Страница 23: ...is properly secured to the air connection on the flue system using the cable tie provided refer image on p 16 and that the rubber cap is in place on the unused air intake Flue pipe of the heater R2731...

Страница 24: ...so ensure the path of the condensate drain hose is kept away from hot surfaces Failure to install the condensate kit correctly may cause damage to the heater and flue system 1 Insert the barbed end of...

Страница 25: ...5 Evolve condensate drain kit connection Complete the gas air hose and flue connection If vertically flueing ensure the condensate tube provided with the EVOKIT03 flue kit is attached to the condensat...

Страница 26: ...bend to overheat The spacers are mandatory and required for correct alignment of the flue components when bends are used When fitted correctly the inner and outer pipes of the ESBEND will be self cent...

Страница 27: ...correctly there is potential for the outer bend to overheat The spacers are mandatory and required for correct alignment of the flue components when bends are used When fitted correctly the inner and...

Страница 28: ...Tel 0800 746 624 http www youtube com rinnainz http facebook com rinnainz Rinnai co nz Arriva Evolve flue installation guide 10726 I...

Отзывы: