Form I-XE/CRGB/RPB, Mfg No. 131782 Rev 4, Page 31

Check installation after start-up

†

†

†

†

†

With the unit in operation, measure manifold gas pressure.
High fire manifold pressure for natural gas should be 3.5" w.c.
and 10" w.c. for propane gas. See Paragraph 11.

†

†

†

†

†

Turn the unit off and on, pausing two minutes between each
cycle. Observe for smooth ignition. On two-stage or modulat-
ing burner systems, manipulate temperature adjustment slowly
up and down to see if control is sequencing or modulating
properly. Raising temperature setting drives burner on or to
full fire.

†

†

†

†

†

 

Observe burner flame at full fire. Natural gas flame should be

about 1-1/2" in height with blue coloring. Propane gas flame
should be approximately the same length with blue coloring.
Yellow tipping may appear on propane gas. If yellow extends
beyond 1/2 to 3/4", adjust air shutters. See Paragraph 29.

†

†

†

†

†

 

Close all panels tightly. With the heater on, check limit control

by completely blocking off distribution air. The limit control
should open within a few minutes, shutting off the gas supply
to the main burners.

†

†

†

†

†

 

If the system is equipped with an optional dirty filter switch,

set the switch. Follow the instructions in Paragraph 35C.

†

†

†

†

†

Place "Owner's Envelope" containing Limited Warranty Card,
this booklet, and any optional information in an accessible
location near the heater. Follow the instructions on the enve-
lope.

DANGER: The gas burner in this gas-fired
equipment is designed and equipped to provide safe,
complete combustion. However, if the installation does
not permit the burner to receive the proper supply of
combustion air, complete combustion may not occur.
The result is incomplete combustion which produces
carbon monoxide, a poisonous gas that can cause
death. Safe operation of indirect-fired gas burning
equipment requires a properly operating vent system
which vents all flue products to the outside
atmosphere. FAILURE TO PROVIDE PROPER
VENTING WILL RESULT IN A HEALTH
HAZARD WHICH COULD CAUSE SERIOUS
PERSONAL INJURY OR DEATH.
Always comply with the combustion air requirements
in the installation codes and instructions. Combustion
air at the burner should be regulated only by
manufacturer-provided equipment. NEVER
RESTRICT OR OTHERWISE ALTER THE
SUPPLY  OF  COMBUSTION AIR  TO ANY
HEATER. Indoor units installed in a confined space
must be supplied with air for combustion as required
by Code and in Paragraph 6A of this heater
installation manual. MAINTAIN THE VENT
SYSTEM IN STRUCTURALLY SOUND AND
PROPERLY OPERATING CONDITION.

lockout control, if the pilot is not established within 120 seconds
(approximately), the unit locks out and must be reset by
interrupting the power to the control circuit (See Lighting
Instructions).

OPTIONAL ACCESSORIES

31. 100% Outside Air Hood (outdoor models)

Outside air hood (Option AS2) is a weatherized, screened hood designed to
be field assembled and installed around the horizontal inlet air opening of the
blower cabinet. The air hood includes factory-assembled louvers (U.S. Patent
4,999,037) designed to help eliminate moisture from the inlet air. Complete
installation instructions are packaged with the air hood option.

FIGURE 29 -
Dimensions
of Optional
Outside Air
Hood

Optional

100%

Outside

Air Hood

43-17/32” (1106mm)

4-5/8”

(117mm)

31-11/32”

(796mm)

14” (356mm)

minimum

NOTE: The width of
the outside air hood is
the same as the width
of the blower cabinet.

CAUTION: It is recommended that the inlet
to the outside air hood NOT be facing into the
prevailing wind. Allow 14" (356mm) minimum
clearance from the bottom of the air hood to
the mounting surface.

Installation Instructions - 100% Outside Air
Hood

Refer to 

FIGURE 30

. All screw ends except those across the bot-

tom should be inside the air hood.
To avoid possible damage, it is recommended that the outside air
hood be installed after the system has been placed on the roof. The
air hood should be installed before the heater is operated. Do not
install the hood while the system (furnace or blower) is in opera-
tion.

1. Top Panel 

- On the air inlet side of the blower cabinet, remove

the factory-installed screws attaching the blower cabinet top.
Slide the air hood

 

top panel underneath the edge of the blower

cabinet top. 

The edge of the air hood top panel must be

between the blower cabinet top and the end panel.

 Reinsert

all of the sheetmetal screws.

2. Side Panels

 - Slide the air hood right side panel into the groove

in the blower cabinet end panel. Be sure that the side panel is
underneath and to the inside of the air hood top panel. Attach to
the blower cabinet and the air hood top using the required num-
ber of sheetmetal screws. Repeat with the left side panel.

inches

mm

75,100,125

53-3/8

1356

150,175

34-1/8

867

200,225

39-5/8

1006

250,300

47-7/8

1216

350

53-3/8

1356

400

58-7/8

1495

Width of Outside Air Hood

Size

Содержание CRGB Series

Страница 1: ...AquaSaver Timer Adjustment 34 Belts 24 Blocked Vent Switch 25 Blower Motors 24 Blower Rotation 24 Burner Air Adjustment 30 Burner Rack Removal 42 Burners 29 Carryover System 29 Check Installation and...

Страница 2: ...rhalogenatedhydrocarbonsorany contaminant silicone aluminium oxide etc that adheres to the spark ignition flame sensing probe b Wiring is not in accordance with the diagram furnished with the heater c...

Страница 3: ...x 19 1 2 495mm Return Air Openings with Optional Cabinet X Hanger Centerline Standard and Optional Blower Cabinet Dimensions inches andmm Gravity Vented Indoor Models XE HXE Gas Connection Natural Pr...

Страница 4: ...side the downturn plenum cabinet For dimensions with downturn plenum cabinet with a cooling coil cabinet see page 6 FIGURE1B Dimensions Outdoor Gravity VentedModel Series CRGB Vent Cap Gas Connection...

Страница 5: ...ottom of cabinet side If system has a cooling coil cabinet add length dimension on page 6 for full system length The two position discharge dampers in Option AQ8 fit in the discharge air opening The d...

Страница 6: ...ownturnPlenumCabinet factoryattachedto either type of Cooling Coil Cabinet Front View DX Coil Cabinet with Horizontal Discharge Option AU3 Liquid Line Connections 7 8 or 1 3 8 5 1 8 130 8 203 3 4 19 3...

Страница 7: ...r from inside the building openings 1 square inch free area per 1000 BTUH Never less than 100 square inches free area for each open ing See 1 in FIGURE 2 2 Air from outside through duct openings 1 squ...

Страница 8: ...the pipe hanger to a 1 threaded pipe See the suspension method on the left in FIGURE 4 As an alternative method the factory installed pipe hanger may be removed and the heater suspended as illustrated...

Страница 9: ...lled 1 Position curb cross rails and curb side rails as illustrated in FIGURE 8 page 10 If there are two side pieces to a side fasten them with splice plates and hardware as illustrated in the splicin...

Страница 10: ...e is horizontal If the system has an AU11 AU12 AU13 AU14 cooling coil cabinet there is a downturn plenum with vertical discharge Options AU2 AU3 AU11 AU12 AU13 and AU14 are not factory installed Optio...

Страница 11: ...should be supported every six feet 1 8M using a non combustible material such as strap steel or chain Do not rely on the drafthood or heater for support of either horizontal or vertical vent pipe 6 V...

Страница 12: ...re horizontal venting is required or where negative building pressure inhibits gravity venting in stall an optional power venter Option CA Use only a power venter provided by the furnace manufacturer...

Страница 13: ...mmended size is 1 2 x1 2 20 gauge FIGURE11B InstallationoftheVentCap includedinthe optionpackage andthefield suppliedPipingandSupports Oval Adapter Assy PN 103025 Venter Seal Plate P N 43446 9 Condens...

Страница 14: ...air duct should come in con tact with masonry walls Insulate around all air duct through ma sonry walls with not less than 1 2 1 is recommended of insula tion Through Unheated Space Insulate all expo...

Страница 15: ...l connections are made disconnect the pilot supply at the control valve and bleed the system of air Reconnect the pilot line and leak test all connections by brushing on a soap solution WARNING All co...

Страница 16: ...ding MUST be made in accordance with the National Electric CodeANSI NFPANo 70 latest edition or in Canada the Canadian Electrical Code Part I C S A Standard C22 1 In addition the installer should be a...

Страница 17: ...ontrols available as part of the gas and air control options Check the wiring diagram and literature supplied with the unit for operation of factory installed optional controls See FIGURE 19 for locat...

Страница 18: ...ND BLOWER MOTOR BRANCH CIRCUIT WIRE SHOULD BE SIZED TO TEMPERATURE RATING OF AT LEAST 105 C EXCEPT FOR MUST BE REPLACED IT MUST BE REPLACED WITH WIRING MATERIAL HAVING A 4 CAUTION IF ANY OF THE ORIGIN...

Страница 19: ...W LEADS CAP RED 8 USE 18 GA WIRE FOR 24 VOLT CONTROL WIRING ON UNIT NONE NOTES 4 CAUTION IF ANY OF THE ORIGINAL WIRE AS SUPPLIED WITH THE APPLIANCE MUST BE REPLACED IT MUST BE REPLACED WITH WIRING MAT...

Страница 20: ...L WIRE AS SUPPLIED WITH THE APPLIANCE 3 DOTTED WIRING AND THE FOLLOWING CONTROLS ARE SUPPLIED AND INSTALLED 2 THE FOLLOWING CONTROLS ARE SUPPLIED AS OPTIONAL EQUIPMENT 1 THE FOLLOWING CONTROLS ARE SUP...

Страница 21: ...N IF ANY OF THE ORIGINAL WIRE AS SUPPLIED WITH THE APPLIANCE 3 DOTTED WIRING AND THE FOLLOWING CONTROLS ARE SUPPLIED AND INSTALLED 2 THE FOLLOWING CONTROLS ARE SUPPLIED AS OPTIONAL EQUIPMENT 1 THE FOL...

Страница 22: ...E SAFETY SWITCH PORTION OF THE CONTROL THE SWITCH ACTION PROVES THE PRESENCE OF THE PILOT FLAME AND ENERGIZED THE A PILOT FLAME ON EACH OPERATING CYCLE THE SENSING PROBE ENERGIZING THE PILOT GAS VALVE...

Страница 23: ...ND ENERGIZES THE MAIN VALVE THE MAIN GAS IGNITES AND THE UNIT FIRES AT LOW RATE 3 ON A CALL FOR HEAT BY THE HIGH STAGE OF THERMOSTAT THE UNIT FIRES AT FULL RATE 4 IF THE FLAME IS EXTINGUISHED DURING M...

Страница 24: ...outlet temperature turn the adjustable half of the pulley outward One turn of the pulley will change the speed 8 10 5 Tighten the setscrew on the flat portion of the pulley shaft 6 Replace the belt an...

Страница 25: ...ing pressure levels off If a restriction or excessive flue length or turns cause the sensing pres sure to become less than the switch setpoint the pressure switch will function to shut off the main bu...

Страница 26: ...e same as the one illustrated 1 Remove the access panel in the ductwork adjacent to the control compartment access panel 2 Element is retained by spring clips 3 Round gasket and metal retaining plate...

Страница 27: ...IGURE24 Signal Conditioner used in Options AG21 and AG40 Carryover Regulator Modulating Valve Single Stage Gas PrimaryGas FlowPressure Switch WhiteLabel 1 1 w c GasFlow PressureSwitch WhiteLabel 1 1 w...

Страница 28: ...per open Is there voltage between Terminal 88 and Terminal 7 Is there voltage between Terminal 4 on ignition permissive relay and Terminal 7 Replace 1 time delay relay Replace ignition permissive rela...

Страница 29: ...6 38mm 79 23 32 18 25mm 7 16 1 16 11mm 1 6 Option AH2 and spark pilot with lockout is Option AH3 NOTE Outdoor units in Canada using propane require lockout Indoor units in U S and Canada using propane...

Страница 30: ...ers cont d INDOOR Gravity Vented Furnace Models XE HXE Natural gas burners are equipped with two flash carryover systems that receive a supply of gas simultaneously with the main burner NOTE A natural...

Страница 31: ...esuppliedwithairforcombustionasrequired by Code and in Paragraph 6A of this heater installation manual MAINTAIN THE VENT SYSTEM IN STRUCTURALLY SOUND AND PROPERLYOPERATINGCONDITION lockout control if...

Страница 32: ...3 Bottom Panel Position the air hood bottom panel so that it is to the inside of the two side panels and above the factory installed support angle Attach to the side panels If the bottom panel does n...

Страница 33: ...ecessary Follow these instructions to field connect the water supply and make neces sary checks and adjustments before operating the cooling module with a lock nut and a sealing gasket Check these fit...

Страница 34: ...ockwise to increase the ON time or counterclockwise to decrease the ON time One complete turn will adjust the cycle by 12 to 14 seconds All Modules Check the reservoir for any water leaks The reservoi...

Страница 35: ...e the water feed line from the downstream side of the ball valve and unscrew the water bleed line barbed hose fitting 3 Force a fresh water supply through the water inlet hose and thoroughly flush the...

Страница 36: ...let DamperOptionsonIndoor ModelsXE HXE FIGURE 41B Location of Controls for30 OutsideAirHood andDamperOptions AR6orAR7 OutdoorModelsonly FIGURE41D Exampleof OutsideAirand Return Air Damper Linkage Damp...

Страница 37: ...w c Heater Filter Size Metal Fillers Size A B C D E F1 F2 75 100 125 20x20 20x20 150 175 20x25 20x25 13 16 13 16 200 225 16x25 16x20 16x25 16x20 250 300 20x25 20x20 20x25 20x20 350 20x25 20x25 20x25...

Страница 38: ...B D D E 25 635mm 20 508mm 20 508mm 25 635mm Size 350 D D D C C Size 400 25 635mm 20 508mm B D Key Filter Code Filter Size A 16 x 20 B 20 x 20 C 16 x 25 D 20 x 25 E 25 x 25 Shaded areas are filter blo...

Страница 39: ...d with op tional discharge dampers the damper motor wires must be connected to the terminal blocks in the furnace electrical compartment If the coil cabinet being installed does not include a downturn...

Страница 40: ...ection remove the center hole plug FIGURE 46H To install side and top fillerpanels remove screws from top corners of both cabinets and the entire row across the cooling coil cabinet Removerowofscrews...

Страница 41: ...or lint accumulation Clean as needed Check the vent system for soundness Replace any parts that do not appear sound Check the wiring for any damaged wire Replace damaged wiring See Paragraph 12 for re...

Страница 42: ...ryover systems with air pressure 40 Cleaning the Heat Exchanger To clean the outer surfaces circulating air side of the heat exchanger gain access by removing the inspection panels in the ductwork or...

Страница 43: ...causes 8 Reset lockout by interrupting control at thermostat 9 Faulty combustion air proving switch 9 Replace combustion air proving switch 10 Activated blocked vent switch indoor system 10 Correct ve...

Страница 44: ...AG39 or AG40 see page 28 For replacement parts refer to Form P X XE for indoor units or Form P RG RP RBL for outdoor units Problem Probable Cause Remedy Pump does not run Unit is 1 Electrical connecti...

Отзывы: