a. Disconnect power to furnace and remove vent connector from furnace outlet collar. Be sure to allow time for vent pipe to cool down

before removing.

b. Restore power to furnace and set room thermostat above room temperature.

c. After normal start-up, allow furnace to operate for 2 minutes, then block flue outlet 100 percent. Furnace should cycle off within 2

minutes.

d. Remove blockage and reconnect vent pipe to furnace outlet collar.

e. Wait 5 minutes and then reset draft safeguard switch.

3. Check pressure switch.

This control proves operation of draft inducer blower.

a. Turn off 115-v power to furnace.

b. Remove control door and disconnect inducer motor lead wires from wire harness.

c. Turn on 115-v power to furnace.

d. Set thermostat to "call for heat" and wait 1 minute. When pressure switch is functioning properly, hot surface ignitor should NOT glow

and control center diagnostic light flashes a 31 fault. If hot surface ignitor glows when inducer motor is disconnected, shut down furnace
immediately. Determine reason pressure switch did not function properly and correct condition.

e. Turn off 115-v power to furnace.

f. Reconnect inducer motor wires, replace control door, and turn on 115-v power to furnace.

4. Check auxiliary limits (when used).

a. Turn off 115-v power to furnace.

b. Remove blower access door.

c. Disconnect red motor lead at blower speed selector. Mark terminal for proper re-connection.

d. Replace blower access door.

e. Turn on 115-v power to furnace. Be sure room thermostat is calling for heat.

f. Allow furnace to operate until auxiliary limit activates, but DO NOT operate furnace longer than 4 minutes.

g. If furnace operates for 4 minutes, check/replace limit switch(es).

h. Turn off 115-v power to furnace.

i. Remove blower access door.

j. Reconnect red motor lead, reset switch, and replace door.

k. Turn on 115-v power to furnace.

F.

Checklist

1. Put away tools, instruments, and clean up debris.

2. Verify manual reset switches have continuity.

3. Ensure blower and control access doors are properly installed.

4. Cycle test furnace with room thermostat.

5. Check operation of accessories per manufacturer’s instructions.

6. Review User’s Manual with owner.

7. Leave literature packet near furnace.

© 1994 RESCO

P.O. Box 1667, Indianapolis, IN 46206

45003r

—20—

Catalog No. 92-33GB-3A5

Содержание GB3AAV

Страница 1: ...a Working Platform 7 Install Furnace 7 HORIZONTAL CRAWLSPACE INSTALLATION 7 8 FILTER ARRANGEMENT 8 9 GAS PIPING 9 10 ELECTRICAL CONNECTIONS 11 12 115 v Wiring 11 24 v Wiring 11 Accessories 11 12 VENTI...

Страница 2: ...aces are available in sizes 50 000 through 135 000 Btuh input capacities The design of the downflow horizontal gas fired furnace is A G A C G A certified for natural and propane gas and for installati...

Страница 3: ...monoxide poisoning explosion fire electrical shock or other conditions which may cause personal injury loss of life or property damage Consult a qualified installer service agency local gas supplier o...

Страница 4: ...nds which include fluoride chloride bromide and iodide These elements are found in aerosol sprays detergents bleaches cleaning solvents salts air fresheners and other household products CAUTION The op...

Страница 5: ...m outdoors See Fig 3 2 All air from outside the structure a If combustion air is taken from outdoors through vertical ducts the openings and ducts MUST have at least 1 sq in of free area per 4000 Btuh...

Страница 6: ...8 19 7 16 21 19 7 8 19 5 8 19 7 16 24 1 2 23 7 16 19 5 8 19 7 16 These dimensions apply when a model CB or CD Evaporator Coil casing is to be installed B Installation On a Combustible Floor 1 Cut and...

Страница 7: ...shield on platform in front of louvered control panel as shown in Fig 7 PROCEDURE 5 HORIZONTAL CRAWLSPACE INSTALLATION The furnace can be installed horizontally with either the LH or RH side up In a c...

Страница 8: ...turn air plenum See Fig 8 and Table 4 for horizontal applications Horizontal filter retainers must be field supplied See Fig 9 for downflow applications Fig 6 Furnace Plenum and Subbase Installed on a...

Страница 9: ...anadian installations must be installed in accordance with NSCNGPIC and all authorities having jurisdiction The gas supply line should be a separate line directly from the meter to the furnace if poss...

Страница 10: ...d only to the male threads of the joints This pipe dope must be resistant to the action of propane gas Install an accessible manual shut off valve upstream of the furnace gas controls and within 72 in...

Страница 11: ...n electrical shock fire or death B 24 v Wiring Make field 24 v connections at the 24 v terminal strip See Fig 11 Connect terminal Y as shown in Fig 13 for proper operation in cooling mode Use AWG No 1...

Страница 12: ...08 230 VOLT SINGLE PHASE WHT BLK WHT BLK If any of the original wire as supplied must be replaced use same type or equivalent wire NOTE Connect Y terminal as shown for proper operation W Y GND THERMOS...

Страница 13: ...Ignitor warm up At the end of the prepurge period the ignitor is energized for a 17 sec ignitor warm up period c Ignition sequence When the ignitor warm up period is completed the gas valve opens per...

Страница 14: ...DISCONNECT SWITCH AND THE FURNACE JUNCTION BOX JB 5 THIS WIRE MUST BE CONNECTED TO FURNACE SHEETMETAL FOR CONTROL TO DETECT FLAME 6 FACTORY CONNECTED WHEN LGPS NOT USED 7 REPLACE ONLY WITH A 3 AMP FUS...

Страница 15: ...e to follow this warning could result in fire explosion personal injury or death 2 Component test The furnace control allows all components except gas valve to be run for a short period of time This f...

Страница 16: ...40 38 39 3 7 3 2 3 5 40 38 39 3 8 3 3 3 6 905 42 3 5 41 42 3 2 3 6 41 42 3 4 3 7 40 41 3 2 3 5 40 41 3 3 3 6 40 41 39 3 4 3 7 3 2 40 41 39 3 5 3 8 3 3 40 39 3 6 3 4 40 38 39 3 7 3 2 3 5 920 42 3 4 42...

Страница 17: ...In the United States gas input on unit rating plate is for altitudes up to 2000 ft Ratings for altitudes over 2000 ft must be 4 percent less for each 1000 ft above sea level To obtain the adjusted al...

Страница 18: ...0 60 62 64 66 68 60 58 56 54 53 120 116 112 109 106 300 290 281 273 265 25 26 27 28 29 144 138 133 129 124 288 277 267 257 248 720 692 667 643 621 70 72 74 76 78 51 50 48 47 46 103 100 97 95 92 257 25...

Страница 19: ...g the heating cycle length NOTE When using an electronic thermostat set cycle rate for 3 cycles per hr E Check Safety Controls The flame sensor gas valve and pressure switch were all checked in the St...

Страница 20: ...did not function properly and correct condition e Turn off 115 v power to furnace f Reconnect inducer motor wires replace control door and turn on 115 v power to furnace 4 Check auxiliary limits when...

Отзывы: