Using a crane
-
Never swing the load over bystanders.
-
Always use special lifting harnesses which should be placed on the boiler.
-
Make sure that during lifting the harness does not damage the draught diverter.
E
5 Installation
5.1 Boiler room
Installation of the R2000 should only be carried out by a recognized installer in accordance with the current
national and local demands, norms and standards.
5.1.1 Siting
Install the boiler as close to the chimney as possible. A plinth base is not required.
To maintain ease of access and therefore ease of maintenance refer to clearances in figure 1.
If these dimensions are not met, maintenance operations could be seriously inhibited.
5.1.2 Boiler room ventilation
The product has to be installed by a recognized installer fully according to the current national
and local demands, norms and standards.
5.2 Unit connections
5.2.1 Gas
supply
The product has to be installed by a recognized installer fully according to the current national
and local demands, norms and standards (see supplement).
Gas connection can be found at the side of the boiler.
Always mount a gas fi lter.
The main gas service cock and gas filter should be supplied by a qualified heating engineer.
Install the main gas service cock and the gas filter as close to the boiler as possible.
The R2000 series of boilers are suitable for connection to a 25 mbar gas network.