background image

 

SunRise 3-Phase 

Home Battery System 

Model: SRS-3xx NS 

 

Installation Manual 

 

Содержание SunRise SRS-3 Series

Страница 1: ...SunRise 3 Phase Home Battery System Model SRS 3xx NS Installation Manual...

Страница 2: ...ith any other charger device or connect any devices directly to the DC battery bus unless approved by RedEarth In the event of a fire evacuate the area and call emergency services A dry agent fire ext...

Страница 3: ...lators 12 Step 4 Electrical Connections 13 4 1 Solar 13 4 2 Battery 13 4 4 Auxiliary remote Earth Fault Alarm option 16 4 5 MSB Meter 16 Step 5 Understanding the Turn ON SHUTDOWN Procedure 17 Step 6 C...

Страница 4: ...PV generated during the day can be exported to the grid which reduces the electicity bill however no electricity can be stored for later use Note that the SunRise is designed so that batteries can ea...

Страница 5: ...332 NS x9 batteries 31 95kWh nominal The max number of batteries available SunRise Weight size and IP rating 414kg with 9x Lithium batteries 32kg per battery 126kg complete without batteries 99kg comp...

Страница 6: ...tteries to deliver the full 10kW of back up power Also do not over load any one phase 4 Up to 3 arrays of PV solar panels are connected to the MC4 conectors pre terminated inside the unit Note that th...

Страница 7: ...a safe location INSIDE LAYOUT The SunRise is divided into three main areas On the Lefthand side LHS is the Inverter in the middle are the batteries and the Battery Management Unit BMU and on the Righ...

Страница 8: ...clips holding it in place to make space Middle area This area is where up to 9 x 3 55kWh HV Pylontech batteries are installed A complete set will have two stacks of batteries with five 5 on the left a...

Страница 9: ...ands suitable for sealing around 25mm flexible conduit o 2x Three pole circuit breakers o Bolts for holding the batteries in place in the rack 2 per battery o Long DC cable Orange red and black plugs...

Страница 10: ...Earth Fault Alarm 4 5 MSB Sungrow meter 5 Understanding Turn on Shutdown procedures 6 Commissioning the system turning on and programming and confirming system operation 7 Activating remote Monitorin...

Страница 11: ...e around the system no doors or windows to comply with current installation standards See image at right if the system is within 300m of the wall Note the material that the wall is made of flammabilit...

Страница 12: ...ctors installed in the system The design of the solar array should take this into account with the two stings connected to the larger MPPT having the same orientation and string length PV2 PV3 3 2 PV...

Страница 13: ...ct polarity and VOC then plug the three strings into the correct MC4s in the system remembering that 2 3 strings need to be the same orientation and length as they are going to the same MPPT 4 2 BATTE...

Страница 14: ...he orange orange plugs which should already be connected to the BMU Then install the supplied shorter battery cables with one orange and one black plug onto the appropriate battery terminals Note that...

Страница 15: ...not overload the EPS circuit in the MSB with not essential loads As the output is floating the neutral cable of GRID side and EPS side must be connected together according to the wiring rules AS NZS_3...

Страница 16: ...fter the main switch in the MSB including the neutral and will work as a pass though of all power going to and from the home The communication between the meter and the system can be made with a CAT5...

Страница 17: ...ll cable entry glands of the SunRise The battery terminal connections on the Battery MCB are tight Check after transportation Check screws holding the lid down are in place and tight Pull on the vents...

Страница 18: ...4 08 2022 The Shutdown Procedure is the reverse of the turn on procedure and is shown below This procedure can be found on the traffolyte label on the RHS of the unit 1 Turn OFF all AC circuit breaker...

Страница 19: ...w 6 1 POWER UP THE SUNRISE SYSTEM Follow the procedure outlined in Step 5 Understanding the Turn ON Shutdown procedure above While it is powering up which can take 5 minutes you can download the Sungr...

Страница 20: ...Date time used for some control operations o Software version confirm latest The screen shots below from the APP show the sequence to reach the System Parameters setting page where these key parameter...

Страница 21: ...ils is also able to access this information to confirm the current settings via Local mode as well as remotely via the iSolarCloud webpage and APP 6 5 TEST THE OPERATION OF THE COMPLETE SYSTEM PRIOR T...

Страница 22: ...EPS loads To activate By pass mode all breakers and isolators should be turned OFF and the Bypass switch should be put in the down position II 6 5 3 Fan Control Adjustment The thermostat is located in...

Страница 23: ...ion the supplied antenna outside Pass the antenna cable through the 16mm hole in the SunRise Use the supplied 16mm gland to seal around the cable Remote monitoring and control is then available via Re...

Страница 24: ...RedEarth You can receive regular relevant communications from RedEarth Other benefits include Access to RedEarth s PPP Private Power Plant and the stream of financial benefits available to the custome...

Страница 25: ...SunRise 3ph NS Installation Manual SunRise 3ph NS Install Version 1 0 Page 25 of 32 Issue Date 14 08 2022 Appendix A Single Line Diagrams Single Line Diagram Power...

Страница 26: ...SunRise 3ph NS Installation Manual SunRise 3ph NS Install Version 1 0 Page 26 of 32 Issue Date 14 08 2022 Single Line Diagram Communications...

Страница 27: ...SunRise 3ph NS Installation Manual SunRise 3ph NS Install Version 1 0 Page 27 of 32 Issue Date 14 08 2022 Single Line Diagram Main Switchboard...

Страница 28: ...50 Hz Max Input Power 20 600 VA Max Input Current 30 0 AAC Rated Output Apparent Power VA 10 000 VA Max Output Power 10 000 VA Max Output Current 15 2 AAC Power Factor Range 0 8 lead 0 8 lag EPS Outp...

Страница 29: ...C No of MPPTs 2 Short Circuit Current ISC 16A 32A 16 16 Max input current 12 5A 25A 12 5A 12 5A PV strings per MPPT 1 2 PROTECTION Overvoltage category III Main II PV Battery Anti islanding Frequency...

Страница 30: ...ation Manual SunRise 3ph NS Install Version 1 0 Page 30 of 32 Issue Date 14 08 2022 Operating Temperature 25 C 60 C Pylontech BMU Specifications Pylontech Lithium Battery H48074 Specifications ISC kA...

Страница 31: ...Manual SunRise 3ph NS Install Version 1 0 Page 31 of 32 Issue Date 14 08 2022 RedEarth Energy Storage Ltd 15 Fienta Place Darra Brisbane QLD 4076 Australia Tel 1800 733 637 Email support redearth ene...

Страница 32: ...SunRise 3ph NS Installation Manual SunRise 3ph NS Install Version 1 0 Page 32 of 32 Issue Date 14 08 2022...

Отзывы: