![Raven Sidekick Pro ISO Скачать руководство пользователя страница 48](http://html.mh-extra.com/html/raven/sidekick-pro-iso/sidekick-pro-iso_installation-and-operation-manual_789032048.webp)
C
HAPTER
5
44
Sidekick Pro™ ISO Installation & Operation Manual
6. Select the Tools icon and select the diagnostics icon to access the Product Diagnostics screen.
7. Select the Master Switch icon to toggle the master switch to the On position and select the ‘Start Prime’ button
from the soft keys area.
8. Verify that the hand valve is set to the recirculation mode and select the ‘OK’ button.
9. The priming procedure will run until the controller detects the pump has primed. If the pump is unable to
prime, the console will end the priming procedure after two minutes and display a “prime time-out” message.
NOTE:
If the console displays an error message during the priming process, verify that the conditions listed
in step 4 are present. If the problem continues, see Chapter 6, Injection Diagnostics and
Troubleshooting, to resolve issues during the pump priming process.
Press the “Stop Prime” button to stop the priming procedure at any time. If the pump fails to prime
successfully after the first attempt, restart the priming procedure. If the pump is still unable to prime
successfully, refer to Chapter 6, Injection Diagnostics and Troubleshooting, for assistance diagnosing
issues with the injection system.
10. When the display shows the prime complete message, touch the ‘Stop Prime’ button to stop the priming
process.
NOTE:
Before beginning an application, verify that the hand valve is set to the injection position and select
the OK button on the UT display to proceed. If the hand valve is not set properly, the pump will not
inject chemical into the main product line during an application.
CALIBRATE THE INJECTION PUMP
Prior to starting a field operation with an injected chemical, verify that the pump is properly calibrated and
operational by performing a pump calibration.
1. Ensure the pump is primed as described in the Prime the Injection Pump section on page 43 before proceeding
with the calibration process.
2. Remove the cover from the injection pump calibrator.
3. Press the calibrator all the way down and replace the calibrator cover.
Содержание Sidekick Pro ISO
Страница 1: ...Sidekick Pro ISO Installation Operation Manual P N 016 0171 509 Rev E 07 17 E29803 Copyright 2017 ...
Страница 8: ...CHAPTER 1 4 Sidekick Pro ISO Installation Operation Manual ...
Страница 16: ...CHAPTER 2 12 Sidekick Pro ISO Installation Operation Manual ...
Страница 46: ...CHAPTER 4 42 Sidekick Pro ISO Installation Operation Manual ...
Страница 70: ...CHAPTER 7 66 Sidekick Pro ISO Installation Operation Manual ...
Страница 80: ...Index 76 Sidekick Pro ISO Installation Operation Manual ...