5.3. Boiler Operation  

Boilers whose functionality has already been verified by the First Heating are started as follows: 

-

 

The power cord must be plugged into the socket. 

-

 

Set the heating water temperature regulator to about 2/3 of its range – the setting can later be adjusted according to the 
temperature of the heating water. The temperature setting f the heating water also affects the speed with which the DHW is 
heated up in the external reservoir. 

-

 

If the boiler will be used in cooperation with an external DHW reservoir, set the reservoir's regulator to about 

1/2 

of its 

range. 

-

 

Check the pressure of the heating water on the boiler's pressure gauge. If the water is cold, the pressure must not be lower 
than set by the red hand (set by the authorised service centre during the First Heating). 

-

 

The SUMMER/WINTER switch is set depending on the time of the year. LÉTO in summer, ZIMA in winter. 

-

 

If the room thermostat regulator is used for regulating the boiler, set the regulator following its instructions for use. 

-

 

Put the main switch to the "ON" position ("I"). Flame will be ignited and the DHW reservoir contents are heated up (if there 
is a reservoir). If the WINTER/SUMMER switch is set to WINTER, when the DHW is heated up, the heating water is 
warmed up and the heating is started, controlled by the heating regulator.  

The HCW (heating-circuit water) heating process is stopped when its temperature has achieved the level pre-set on the heating 
operation regulator, or if the room temperature has achieved the level pre-set on the room thermostat (i.e. temperature of air in the 
room in which the thermostat is installed). 

The DHW (domestic hot water) heating up is stopped when the temperature pre-set on the DHW reservoir regulator is achieved, 
or the HCW temperature has achieved the level pre-set on the heating operation regulator. 

If the boiler does not ignite and the defect indicator is off, the operation is stopped due to one of the operational reasons we have 
just described; the heating will automatically start again as soon as the DHW or HCW cools down, or when air temperature 
decreases in the room in which the room thermostat is installed. 

If the boiler does not start even after a long time and does not respond to increasing of the pre-set temperature value, there is a 
defect and a specialised service centre should be called. 

If the boiler does not start and the defect indicator is on, follow the instructions in Description of Controls. 

5.4. Breaks in Boiler Operation 

If the operation of the boiler is to be stopped for a shorter period of time, simply set the main switch to the 'off' position. Before a 
longer break between operations, unplug the electrical cord and shut off the gas supply. You can leave water in the boiler if there 
is no risk of freezing, otherwise you should discharge water from the boiler and the heating circuit. 

 

l

 

If at all possible, discharge water only from the boiler when disassembling the system – the heating circuit is protected from 
corrosion if the HCW is left in. 

6. Boiler Maintenance 

6.1. Professional Maintenance  

The boiler should be checked and adjusted by a professional organisation at least once a year, preferably before the beginning of 
the heating season. Such service inspection cost is not included in the guarantee. A list of recommended steps is specified in the 
Service Booklet. 

Most of the steps are concerned with checking the condition and functions of the burner, adjustment of power output, checking 
the tightness of flue-gas duct connections (with repairs if necessary), cleaning of burner nozzles (if necessary – the cleaning must 
be done carefully, as the inner diameter of the nozzles must not be changed by the cleaning), and cleaning the heat exchanger in 
the boiler. 

 

 

Checking the functionality of the emergency and flue-gas thermostats is very important – these elements must also be 
checked after each servicing on them. 

 

12

Содержание 20 KLO

Страница 1: ...By www heating spares co Tel 0161 620 6677 Instructions for Use and Installation of Cast Iron Boilers PROTHERM 20 30 40 50 60 KLO BEAR Version Protherm s r o ltd Pplk Plju ta 45 909 01 Skalica Slovak...

Страница 2: ...ig 3b Vertical Control Panel 11 Fig 4a Electric Wiring Diagram of PROTHERM 60 KLO 18 Fig 4b Electric Wiring Diagram of PROTHERM 20 30 40 50 KLO 18 Fig 5a Regulation elements of SIT 843 combined gas ar...

Страница 3: ...Do not remove or damage any labels or markings on the boiler 9 The boiler complies with all Czech applicable regulations If it is to be used in another country deviations in the regulations have to b...

Страница 4: ...ted if the valve s motor is not active gets no voltage The boiler s manufacturer supplies both DHW reservoirs 100 150 200 l and suitable three way distribution valves l DHW heating takes preference ov...

Страница 5: ...onnection Dimensions 1 Control panel 2 HCW pressure measuring point 3 HCW temperature measuring point 4 Boiler cast iron body 5 Combined gas armature 6 Water filling and discharging 7 Burner plate dis...

Страница 6: ...the required and actual parameters i e the state of the boiler and the heating circuit the gas pipe leading out of the armature is part of the burner plate with 2 to 6 nozzles one per each burner tube...

Страница 7: ...3 Chimney flange 4 Flue gas duct with draft dampener 5 SKKT chimney draft control system 6 Outgoing HCW 7 Gas supply 8 Cast iron elements 9 Incoming HCW 10 Combustion chamber 11 Secondary air supply 1...

Страница 8: ...ce is solved by ventilation openings of sufficient size Gas appliances with flue gas removal to chimneys must not be in rooms in which negative air pressure is created by ventilation fans 3 4 Flue Gas...

Страница 9: ...pes so that the pipe fixtures on the boiler should not be affected by any pressures or tensions The fixtures on the boiler have outside male threads l Closing valves are recommended to be installed on...

Страница 10: ...gas piping i e electricity supply to the boiler must be stopped in addition to using the boiler switch e g by unplugging b Stopping the boiler whenever flammable or explosive vapours appear even if t...

Страница 11: ...such defects may be caused by not igniting the flame no gas or the chimney draft control system if there is none or too low a draft or emergency thermostat if the HCW temperature is above 100 C may h...

Страница 12: ...lements flue gas and emergency temperature thermostats disabled or replaced with elements different from those specified by the manufacturer Users are not allowed to tamper with the safety elements He...

Страница 13: ...regulator If the boiler does not ignite and the defect indicator is off the operation is stopped due to one of the operational reasons we have just described the heating will automatically start agai...

Страница 14: ...and persons under the influence of drugs or otherwise incapable must be prevented from operating the boiler 7 2 Quality Compliance The boiler s quality compliance is provided by and checked within the...

Страница 15: ...olted on a palette Do not let any forces act on the casing when handling or when storing the boiler For handling without a palette the base can be used cf Chapter 2 For storage normal conditions have...

Страница 16: ...eedle on the boiler pressure gauge 3 9 Electrical Connections of Boiler The electrical installation cabinet and the service part of the control panel are accessible when the top panel of the boiler is...

Страница 17: ...nufacturer These elements must also be checked after each servicing on them 5 Boiler Operation 5 1 Boiler Preparation and Start Check water pressure on the boiler pressure gauge Turn the gas supply va...

Страница 18: ...rocedure must be followed Only authorised service centres are allowed to carry out the conversion The following steps are to be followed 1 Dismount the burner from the boiler 2 Replace the nozzles wit...

Страница 19: ...ig 4b Electric Wiring Diagram of PROTHERM 20 30 40 50 KLO HV Main switch PO1 Electrical fuse SP Power stage switch TL1 RESET button DT1 Emergency state indicator HT Emergency temperature thermostat TS...

Страница 20: ...1 620 6677 Fig 5a Regulation elements of SIT 843 combined gas armature for boilers 20 30 40 50 KLO a Input b Output 1 Setting screw for maximum 2 Setting screw for minimum Fig 5b Regulation elements o...

Страница 21: ...2 3 Flue gas removal manner to chimney to chimney diam outlet mm 130 130 Min required draft in chimney Pa 2 Flue gas temperature natural gas C 100 LPG C 95 Weight flowrate flue gas g s 13 3 19 8 Effi...

Страница 22: ...ue gas removal manner to chimney to chimney to chimney diam outlet mm 150 180 180 Min required draft in chimney Pa 2 Flue gas temperature natural gas C 100 LPG C 95 Weight flowrate flue gas g s 26 6 3...