93-520-20 Issue 3.3
Page 16 of 60
CirrusPro Engineer’s Manual
3.0 Commissioning
Before starting to commission any unit, it is necessary to verify that all the external wiring and pipe
work has been fitted correctly and that the pipe work matches the pipe calculation results.
The commissioning process is carried out using a PC. Most commissioning actions can be carried out
with a display panel (DP), when fitted.
3.1
Pre Commissioning
3.1.1 Information Required for Commissioning
1. Details from the contractor should provide information relating to the input and output
requirements of the unit or units. This information is necessary for the correct operation and
settings of each detector.
2. A copy of the pipe calculation results to set the Air Flow and to confirm the transport times.
3.1.2 Fitting the Equipment
The CirrusPro 100 and 200 are dispatched with the vacuum pump packaged separately. This must be
fitted prior to the power being connected. It is fitted in the lower left hand side of the unit, the pipe is
connected from the cloud chamber and the power connector is fitted to the PCB.
On all models, it is necessary to fit the water bottle with the pipe attachment top and attach the water
fill pipe. The water bottle top has a twist on connector. Mounting pads are provided to hold the bottle in
place.
Pump Pipe
Vacuum Pump
Power Connection
Cloud
Chamber
Vacuum Pump
Water Bottle
Water Fill
Pipe