10
11
Step 3:
Make sure that the door leaf does not jam in the opening and closing
movement. The sliding gate rail shall be perfectly rectilinear, level, unobstructed
periodically from any element or dirt which makes it difficult to slide the pulleys
over their entire length, as shown in the figure below.
INSTALATION AND FIXATION OF THE AUTOMATOR
Before installing the automation system, remove any unnecessary cables and
disable any equipment or system connected to the mains.
EQUIPMENT DIMENSIONS
The correct operation of this equipment depends on the instructions in this
manual. To fix the equipment, proceed as follows:
Step 1:
Make sure that the floor is firm enough so that the equipment can be
screwed so that it is level. If it does not comply with the requirement, provide a
concrete base, following the guidelines below:
Step 2:
Base dimensions should be appropriate for the dimensions of the
automation. The concrete base should be at a distance of approximately 20 mm
from the face of the door leaf.
Step 3:
Once the conditions have been met, open entirely the gate and position
the automator next to the face of the gate leaf, obeying the 50 mm measurement
between the leaf end and the automator.
GATE LEAF
SIDE VIEW
CONCRETE BASE