.Equipment Installation
3.1
Site and Environment Requirements
Before UPS installation, the site and environment of equipment room should
meet the essential conditions for safe and normal operation of equipment as
defined in this section. If the customer’s site conditions are not accord with the
minimum requirement of safe equipment operation, the customer should make
corresponding changes to the site conditions, and install the equipment only
after meeting the conditions of safe and normal equipment operation.
3.1.1
Site Requirements
The site conditions should accord with the essential conditions of safe and
normal equipment operation as stated in this section.
1
.
The equipment room must be equipped with applicable and effective fire
apparatus;
2
.
The commercial power, which supplies power for UPS, should be equipped
with dedicated air switch or utility socket;
3
.
Strictly prohibit to store dangerous things, such as inflammable things,
explosive things in the equipment room;
4
.
Before equipment installation, the ground wire should be prepared. The
voltage of neutral wire and ground wire of commercial power cannot
exceed 5V;
5
.
The civil engineering construction of the equipment room should be
completed totally, and the floor should be sclerotic. The site must be tidy
and dry without dust.
3.1.2
Environment Requirements
Ambient temperature: 0
℃~
+40
℃
;
Relative humidity: 0%RH
~
95%RH, no condensation;
Cooling mode: air-cooling;
Verticality: no shock with orthogonal rake not exceeding 5º.