3.2
Procedures of Dismantling Cases
When installing the equipment, the packing should be removed after carrying
the equipment to the installation site. The packing of UPS equipment and
fittings (battery, etc.) should be wooden case and carton. Check the UPS
equipment and fittings against the shipping list.
If the equipment or fittings are damaged during transportation or the equipment
and fittings are not accord with the ordering contract, make site record in time
and immediately contact the local office or distributors.
Refer to Table 3-1 for the equipment configuration.
Table 3-1 List of Equipment Configuration
Item
Description
Unit
Qty.
Remarks
1
AC wire
Piece
1
3KVA is line bank
2
Fuse
Piece
1 3KVA N/A
3
Software
Set
1
Optional
4
User’s Manual
Copy
1
Enclosed in grip bag
5
Packing list
Copy
1
Enclosed in grip bag
6
Warranty Card
Copy
1
Enclosed in grip bag
7
Battery
expansion line
Piece
1
Standard time beckup model N/A
3.3
Installation of UPS
Because the main unit size of (3kVA) stand
ard time-delay model and
long time-delay model is small, the UPS can be placed on the flat surface
directly without other fixing or installation. For convenient operation,
maintenance and heat emission of the equipment, there shall be at least
30cm~50cm room space reserved around the machine frame and 50cm above
the upper machine frame. The vent fan shall be installed beside the battery.
Keep good interior ventilation. The service life of the battery is the longest
when the battery is used under normal temperature(20
℃
). Recommend to
install air-conditioning equipment in equipment rooms with allowed conditions.
Refer to Fig. 3-1 for the precautions of UPS installation and use.