Perlight Solar IRT Integrated Roof Tile Installation Manual
16
www.perlight.com
V.03.2021 C2.6
Installation Steps (Example)
Side Flashing installation
Flashing-Left (3-4) & Flashing Right (3-5)
are symmetrically
designed and are matched with
PLM-**MB-24 (L) (1-1) & PLM-
**MB-24 (R) (1-3)
Flashing Edges.
Flashing-Left & Flashing Right
slide into the outer Flashing Edges of
PLM-**MB-24 (L) & PLM-
**MB-24 (R)
Flashing Edges from the bottom.
Begin with the bottom row and work upwards.
Installation of the second row flashing:
The installation of second row flashing is the same as the first, both
slide into the module outer Flashing Edges. A partial lower area of
the second flashing covers the first to form an overlapping area.
Side Flashings are designed for the upper flashing to overlap
the lower Flashing.
After Flashing-Left and Flashing-Right are all installed, attach
Seal
Strip 02 (2-5)
to the flashing.
Seal Strip 02
can be cut later, when laying roof tiles to fill any gap
between the roof tiles & flashing as shown.