![Perlight Solar IRT Скачать руководство пользователя страница 15](http://html1.mh-extra.com/html/perlight-solar/irt/irt_installation-manual_1530978015.webp)
Perlight Solar IRT Integrated Roof Tile Installation Manual
15
www.perlight.com
V.03.2021 C2.6
The module Lower Frame slots directly into the Upper
Frame of the module in below row.
Remember when installing the first module in each
row, PLM-**MB-24 (L) (1-1) must be used.
The figure on the left shows the Lower Frame of the
module (Blue) slotting into the Upper Frame (Yellow)
of the already installed module and Seal Strip 01 (2-6)
(Red).
Due to the installation of Seal Strip 01 (2-6), it may
be difficult to pull down the module after placement.
To ensure alignment of the upper and lower joining
modules, rubber hammer can be used to tap the
upper edge of the module. Use a wooded strip with
equal length to the module against the Upper Frame
and
gently tap
into final position.
Do not strike with
excessive force and do not strike the front side of
the module.
Use Self-Tapping Fixings 5*30mm (2-2)
to lock modules tightly after placement &
follow the
same steps to add Mid-Clamps as in the first row.
The installation of middle modules in each row is the
same.
Also note the final module of the row must be PLM-
**MB-24 (R) (1-3).
The process is completed the same as the bottom row
including installation of Seal Strip 01 (2-6).
Installation Steps (Example)
Installing modules above bottom row