Set the first roofing section
for the other side in place as
was done for the first section.
These two sections can now
rest against each other on
their ridge boards. Now, con-
nect these two ridge boards
together with one 2 1/2"
screw, staggered every 16"
apart. Make sure the ends of
panels are flush.
Once all the rafters are con-
nected, install the vertical
board of the gable sunburst
design. Make sure it is in the
center of the building. Fasten
with four 2 1/2" screws. Two
on top, two on bottom.
Lift the first section into place,
making sure the end is resting
on the top plate and against
the fascia board. The 12" over-
hang section should be against
the inside of the top plate and
flush with the outside of the
fascia board as shown. Use a
prop board to hold it in place.
(Prop board not included)
Do the same process with
the remaining sections until
all roofing sections are in
place. Once all sections are
in place, connect the inside
seams of all opposing sec-
tions. Do this by driving 2 1/2"
screws every 16" along the
seams.