ILP 25/33 Installation Manual
Rev. 1.4
- 36 -
12.3
Final Steps of Installation
1. Battery Connect: Connect battery cable to batteries, aux batteries to power the liftgate. Refer to
electrical installation on Section 13.
2. Cycle Gate: Cycle gate several times to assure proper alignment.
3. Weld Gate:
Complete welding of gate. Weld all contact areas 100% with ¼” fillet welds.
4. Remove Retaining Bolts and Welds: Lower the gate down to the ground, and remove the retaining
bolts or welds that hold the swing fixture fixed to the mount tube on curb side and street side.
4a. Removing Retaining Bolts: Remove the bolt and nut from the left and right sides of the liftgate.
Discard hardware,
Fig.30
4b. Removing Retaining Welds: Remove the welds to separate the swing fixture from the mount
tube by grinding off the welds,
Fig.31
. Touch up any grinded surfaces with paint.
Swing
Fixture
Removal of Retaining Bolts
Retaining
Bolt
Under View of
Mount Frame
Nut
Swing
Fixture
Removal of Retaining Welds
Retaining
Welds
Under View of
Mount Frame
Retaining
Welds
Platform will not tilt to the ground if the retaining welds or bolts are not removed.
Fig.30
Fig.31