Operating Manual and Inspection Book
TOP LIFT TSK 12000 DJ
- 39 -
• An on-site electrical connection of 1 ~/N + PE, 230V, 60Hz is to be provided.
The supply line is to be correspondingly secured on-site. The connection point
is located on the electrical boxes.
• To protect the electrical cable all cable conduits are to be fitted with cable
sleeves or flexible plastic pipes.
• After successful lift installation and before first commissioning, the operating
company must have the lift grounding conductors inspected onsite accord-
ing to IEC regulation (60364-6-61). An insulation resistance test is also recom-
mended.
8.2 Assembly of the lift
When assembling the rail lift (in particular the fixture on the lifting post
pipes) ensure that the proper fastening screws are used; also comply
with the minimum screw-in depth. Otherwise this can lead to damage
and endanger life and limb.
Ensure that the listed screws are tightened to the required torque. For
this, see the torque table in the maintenance plan.
The fastening screws are to be checked before first commissioning and
as needed for the annual safety inspection and maintenance.
Fastening screws required for Nußbaum post lifts
(Connecting from the lifting post pipe to the fixture)
Type
Fastening
screws
Standard
Tensile
strength
Number of
pieces per lift-
ing post
Number of
pieces per lift
TSK 12000
M24x150*
DIN 912
12.9
4
8
* Screws and spring washer galvanised
8.3 Commissioning
Before commissioning, a single safety inspection must be done (use the "sin-
gle safety inspection" form)
If the lift set up is done by a specialist (factory trained assembler) then he can also do
the safety inspection. If the set up is done by the operating company then a specialist
must be tasked with the safety inspection. The specialist confirms seamless operation
of the lift on the set up protocol for single safety inspection and releases the lift for use.
After commissioning, the set up protocol must be completed and sent to the
manufacturer.
!
!
Содержание TOP LIFT TSK 12000 DJ
Страница 2: ......
Страница 9: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 9 ...
Страница 15: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 15 3 2 Data sheet ...
Страница 16: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 16 ...
Страница 17: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 17 ...
Страница 18: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 18 3 3 Hydraulic plan ...
Страница 20: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 20 3 4 Pneumatic plan ...
Страница 22: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 22 ...
Страница 23: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 23 ...
Страница 24: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 24 ...
Страница 25: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 25 ...
Страница 34: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 34 7 1 Lift maintenance plan ...
Страница 35: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 35 ...
Страница 36: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 36 ...
Страница 37: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 37 ...
Страница 51: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 51 10 Spare part list ...
Страница 52: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 52 ...
Страница 53: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 53 ...
Страница 54: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 54 ...
Страница 55: ...Operating Manual and Inspection Book TOP LIFT TSK 12000 DJ 55 ...