27
4.10.1
General Installation instructions using the 44658-51
Figure 29 – Cable Routing Overview (Using 44658-51)
1.
Connect the UC4 power cable
(C10
) to the
UC4+ Control Panel in the cab. Ensure that
both plugs (
P16
and
P4
) are connected to
the panel
.
2.
Route the 22-pin AMP receptacle (
R22
) of
C10
to the exterior of the cab.
3.
Connect the 22-pin AMP plug (P22) of
the extension cable (C11) to R22 of C10.
Connect at the hitch. This connection will
provide your hitch disconnect.
4.
Run cable C11 from the hitch to the rear
of the sprayer.
5.
Install the sensor branch cable (
C02
)
along the boom between the ultrasonic
sensors. Be sure to route the cable through
the boom to avoid damage to the cable
during field operation or boom folding.
Connect cable C02 to cable C02A. Connect
cable C02A to cable C11.
6.
Route the 6-pin and 4-pin tower connectors
(
T6
and
T4
) of
C11
in the vicinity of the
Job-com box.
Ensure power to the Job-com is turned
off.
7.
If the sprayer uses one forward/reverse valve
and a number of cartridge valves (HARDI
DH) turn ON the DIP switch of
C12A
(Figure 30). Otherwise leave the switches
OFF (HARDI DAH). There is denotation on
the switch. Turn BOTH switches either ON
or OFF.
Содержание UC4+ Roll Control
Страница 11: ...7 Figure 4 Hydraulic Plumbing Schematic ...
Страница 40: ...36 6 3 ITEM C3 44656D CABLE VALVE VARIABLE RATE DT ...
Страница 41: ...37 6 4 ITEM C10 44658 52 CABLE UC4 BC POWER C10 HARDI ...
Страница 42: ...38 6 5 ITEM C11 44658 50 CABLE UC4 BC EXTENSION C11 HARDI ...
Страница 43: ...39 6 6 ITEM C12A 44658 51 CABLE UC4 BC INTERFACE HARDI DAH ...
Страница 44: ...40 6 7 ITEM C12 44658 78 CABLE UC4 BC INTERFACE HARDI DAH 09 ...