6. Transport, storage and long-term storage
6.1 Transport
Any work regarding transportation, storage, siting, installation, commissioning, operation, service, and
maintenance must be carried out by qualified personnel only.
Any damage identified after delivery must be communicated immediately to the transport company,
if appropriate, commissioning/ activation must be excluded. The transportation of the gear unit must be carried
out in a manner where personal injury and damage to the gear unit are avoided.
Danger
:
Imminent danger! May result to serious bodily injury.
(Danger of crushing bodies or body parts)
Transport may only be carried out using suitable and designated means of transport.
When lifting eyebolts, they may only be attached to the intended holes with approved, adequately dimensioned
lifting equipment. There must be no diagonal pull.
Installation-specific provisions and requirements must be complied with.
Relevant national and regional regulations for safety, accident prevention and environmental protection must be
complied with.
6.2 Storage conditions
DynaGear
gear units must only be stored in a closed condition, in a dry, dust-free, and low vibration
(to avoid bearing damage) environment, without direct sunlight and at a temperature between -25 and +50°C.
Series gear units can be stored for up to one (1) year.
Always check the oil level before taking the gear unit into service.
6.3 Long-term storage
If storage is planned for more than 1 year, the "long-term storage" version is recommended.
These gear units can be stored for up to 5 years maximum.
The external preservation is carried out by applying a permanent preservative agent.
The internal preservation is carried out with a synthetic gear oil based on PAO.
It is advisable to rotate the gear unit at regular intervals to prevent the bearings from sticking (jamming),
the rotation also counteracts standstill marks and the shaft seals do not stick or become brittle.
6.4 Preparation of commissioning
Drain the oil and replenish with fresh oil before commissioning. If taken into service before the 5 years have
elapsed, its function is guaranteed.
If commissioned at a date later than 5 years after being put into storage, the roller bearings, sealing elements
and gear oil must all be replaced. For this purpose, it is probably best if you return the gear unit to our service
department.