TESTING AND COMMISSIONING
These are the most important phases of automation set-up to ensure maximum system safety.
They must be done by a qualified technician who agrees to run the tests and check the solutions to any risks present, as well as checking com-
pliance with regulations, standards and the law: in particular, the requirements of EN 13241-1, EN 12445 and EN 12453.
Any supplementary equipment must be tested separately for operation and interaction with WIDE: refer to the respective user manuals.
6.1 - Testing
The testing procedure can also be performed as a periodic check of the automation devices. Each component of the system (sensitive edges,
photocells, emergency stop, etc.) requires a specific testing phase. To do so, follow the procedures given in the instruction manuals.
Run the test as follows:
01.
Ensure that all specifications in Section 1 “WARNINGS” have been observed in full
02.
Check the correct balancing of the boom: Section 3 - installation (step 13)
03.
Check the correct operation of the manual release and lock, based on the model purchased:
WIDE
S
WIDE
M
WIDE
L
WIDE
S
WIDE
M
WIDE
L
WIDE
S
WIDE
M
WIDE
L
WIDE
S
WIDE
M
WIDE
L
WIDE
S
WIDE
M
WIDE
L
WIDE
S
WIDE
M
WIDE
L
WIDE
S
WIDE
M
WIDE
L
WIDE
S
WIDE
M
WIDE
L
04.
Using the key selector or the command push button, do some tests on the Opening, Closing and Stop of the barrier mechanism and
check that the movement corresponds to the commands given: it is recommended that you perform several tests to assess the move-
ment of the boom and whether any errors have occurred in assembly or adjustment and whether there are any particular points of
friction
05.
Verify the correct operation of all safety devices in the system (photocells, sensitive edges etc.): when a device is activated, the OK LED
on the control unit flashes 2 times quickly, confirming that the control unit has recognised the event.
06.
Check the operation of the photocells and for any interference with
other devices: you need one or two blocks of hard material (e.g.
wooden panels) measuring 70 x 30 x 20 cm. Each block must
have three sides of reflective material (e.g. mirror or white gloss
paint) one for each dimension, and three sides of an opaque mate-
rial (e.g. matt black paint).
To test the photocells positioned at 50 cm from the ground, the
block must be placed on the ground or raised to 50 cm to test the
photocells positioned at 1 m from the ground.
If the test is on a pair of photocells, the testing block must be
placed directly under the centre of the boom with the 20 cm sides
facing the photocells and moved along the entire length of the
boom.
300
200
700
500
300
200
700
300
200
700
500
150
150
If the boom is moving towards the closed position, proceed as follows:
r - cut the mains power supply to the automation
s - rotate through 180° the motor connector (MOTOR - Fig. 5)
t - supply mains power to the automation
4
3
p
15
14
13
12
11
10
9
8
7
6
5
q
ON
OFF
1 2 3 4 5 6 7 8 9 10
r
OFF
t
ON
s
180°