GSM-204-423
Configuring battery backup to supply two BTS cabinets
31st Oct 01
Installation & Configuration: Horizon
macro outdoor
68P02902W03-A
CONTROLLED INTRODUCTION
Inst. 5–15
Refitting the
power
distribution box
The procedure for refitting the power distribution box is as follows:
1.
Connect the power cables for the heater mats and the fan to the external
alarm interface board.
2.
Connect the alarm cables for the door microswitch to the external alarm
interface board.
3.
Mount the power distribution box onto the underside of the lid and secure
in position using the M4 nuts.
4.
Connect the longer pair of battery cables from the power distribution box
to their terminals on battery bank 1, row 2. The blue cable connects to
negative and the black cable connects to positive.
5.
Install the bank 2, row 1 battery tray, followed by the bank 2, row 2 battery
tray and then remake the terminal connections between the two rows
(refer to
Installation and Configuration: (GSM-204-423) Installing
batteries in the auxiliary equipment housing if necessary. Connect the
remaining pair of battery cables to the positive and negative terminals on
the top bank of batteries.
6.
Connect the alarm signal cables to PL1, PL2 and PL3 on the front of the
power distribution box.
7.
Connect the dc power cables from one BTS cabinet to the rear pair of
Anderson connectors on the power distribution box. Connect the dc power
cables from the second BTS cabinet to the front pair of Anderson
connectors.
8.
Switch on the circuit breakers on the front of the power distribution box
and then close the lid and the cabinet door.
9.
Switch on the EXT BATT circuit breaker on the dc circuit breaker panel in
the main cabinet.
The procedures for configuring the battery backup to supply two BTS cabinets
are now complete.
Содержание Horizonmacro outdoor
Страница 126: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 128: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 140: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 142: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 160: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 162: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 178: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 180: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 206: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 208: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...