GSM-204-423
Configuring battery backup to supply two BTS cabinets
31st Oct 01
Inst. 5–12
Installation & Configuration: Horizon
macro outdoor
CONTROLLED INTRODUCTION
68P02902W03-A
Configuring battery backup to supply two BTS cabinets
Introduction to
configuring
battery backup
The circuit breakers in the power distribution box are linked in parallel when
supplied. The links must be removed if two BTS cabinets are to be connected to
one auxiliary equipment housing.
The power distribution box must be removed to gain access to the parallelling
links and refitted after the links have been removed.
Removing the
power
distribution box
The procedure for removing the power distribution box from the auxiliary
equipment housing is as follows:
WARNING
The batteries are capable of supplying high short circuit
currents and as such provides a high energy hazard.
Isolate the auxiliary equipment housing from the main
cabinet by switching off the EXT BATT circuit breaker on
the dc circuit breaker panel in the main cabinet before
commencing work.
1.
Open the cabinet door, release the lid latch and raise the lid.
2.
Switch off the circuit breakers on the front of the power distribution box
and then disconnect the dc input cables, (if fitted), from the Anderson
connectors on the left side of the power distribution box.
3.
Unplug the alarm signal cables from PL1, PL2 and PL3 on the front of the
power distribution box.
4.
Disconnect the two cables which connect the top bank of batteries (bank
2, row 2) to the power distribution box and tie the cables safely out of the
way. Undo the battery terminal connections between bank 2, row 2 and
bank 2, row 1 and then remove the row 2 battery tray, followed by the row
1 battery tray.
5.
Disconnect the two cables which connect battery bank 1, row 2 to the
power distribution box and tie the cables safely out of the way.
6.
Undo the eight M4 nuts which secure the power distribution box to the lid
and then remove the box.
7.
Unplug the door microswitch alarm cable from the external alarm interface
board.
8.
Unplug the power cables for the heater mats and the fan from the external
alarm interface board.
The parallelling links can now be removed.
Содержание Horizonmacro outdoor
Страница 126: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 128: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 140: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 142: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 160: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 162: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 178: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 180: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 206: ...GSM 204 423 31st Oct 01 ii Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...
Страница 208: ...GSM 204 423 31st Oct 01 iv Installation Configuration Horizonmacro outdoor CONTROLLED INTRODUCTION 68P02902W03 A ...